Austin — Short and long-term lane, road closures, and detours that may impact drivers along US 183 and adjacent roadways in east Austin.

Below is an overview of the 183 South project’s lane, road, and ramp closures. Work continues along US 183, including bridge construction, roadway installation, sound wall work, utility work.

The Central Texas Regional Mobility Authority is an independent government agency created in 2002 to improve the transportation system in Williamson and Travis counties.

The Mobility Authority is overseen by a seven-member Board of Directors. The Governor appoints the Chairman, and the Travis and Williamson counties Commissioners Courts each appoint three members to serve on the Board.

 

 

 

US 183 Short & Long Term Closures & Detours

*Dates are subject to change based on weather and other circumstances.

..

Short Term

LANE CLOSURE — 5/2/21 to 5/3/21 — ROADWAY STRIPING
Sunday (5/2) 6 p.m. to 6 a.m., US 183 northbound frontage road will be reduced to one lane from MLK Blvd. to Manor Springdale Rd.

LANE CLOSURE — 5/2/21 to 5/4/21 — ROADWAY STRIPING
Sunday (5/2) 6 p.m. to 6 a.m., Monday (5/3) 8 p.m. to 6 a.m., US 183 northbound Exit to Airport Blvd. will be closed at Montopolis Dr. Detour via 183 north frontage road to Boggy Creek U-turn to US 183 south to Airport Blvd., 5th St., 7th St. and Cesar Chavez.

LANE CLOSURE — 5/3/21 to 5/6/21 — PAVING
Monday (5/3) 6 a.m. until Thursday (5/6) at 3 p.m. US 183 southbound on-ramp will be closed at MLK Blvd.

LANE CLOSURE — 5/3/21 to 5/5/21 — GUARDRAIL WORK

Monday-Wednesday (5/3-5/5) 9 a.m. to 3 p.m., US 183 right frontage lane in both directions will be closed from 51st to Manor Springdale Rd.

LANE CLOSURE — 5/3/21 to 5/5/21 — GUARDRAIL WORK
Monday-Wednesday (5/3-5/5) 9 a.m. to 3 p.m., US 183 southbound exit ramp to Loyola the right lane will be closed from Manor Springdale to Purple Sage.

LANE CLOSURE — 5/3/21 to 5/5/21 — GUARDRAIL WORK
Monday-Wednesday (5/3-5/5) 9 a.m. to 3 p.m., eastbound Manor Springdale Rd. right turn lane will be closed at US 183.

LANE CLOSURE — 5/3/21 to 5/6/21 — GUARDRAIL WORK
Monday-Thursday (5/3-5/6) 9 a.m. to 3 p.m., US 183 right frontage lane in both directions will be closed from 51st to Manor Springdale.

 LANE CLOSURE — 5/3/21 to 5/5/21 — GUARDRAIL WORK
Monday-Wednesday (5/3-5/5) 9 a.m. to 3 p.m., By-pass at MLK Blvd. in both directions the right lane will be closed.

 LANE CLOSURE —5/3/21 to 5/4/21 — SIGN INSTALLATION
Monday-Tuesday (5/3-5/4) 9 a.m. to 3 p.m., US 183 southbound right mainlane will be closed from Patton to SH 71

LANE CLOSURE — 5/3/21 to 5/7/21 — BRIDGE CONSTRUCTION
Monday-Friday (5/3-5/7) 9 a.m. to 3 p.m., US 183 northbound to Airport, 7th St., and Cesar Chavez the right lane will be closed at US 183.

LANE CLOSURE — 5/3/21 to 5/5/21 — BRIDGE CONSTRUCTION
Monday-Wednesday (5/3-5/5) 9 a.m. to 3 p.m., US 183 southbound right mainlane will be closed from Loyola to MLK Blvd.

RAMP CLOSURE — 5/3/21 to 5/4/21 — PAVING
Monday (5/3) 8 p.m. to 6 a.m., US 183 northbound on ramp will be closed at Purple Sage. Detour through signalized intersection at Manor/Springdale Rd.

ROAD CLOSURE — 5/3/21 to 5/5/21 — PAVING
Monday-Tuesday (5/3-5/4) 8 p.m. to 6 a.m., Airport Blvd. southbound ramp to US 183 will be closed. Detour via 7th St. ramp to US 183 southbound.

RAMP CLOSURE — 5/3/21 to 5/8/21 — PEDESTRIAN BRIDGE CONSTRUCTION
Monday-Friday (5/3-5/7) 8 p.m. to 6 .m., 183 Toll southbound will be closed at Hudson St. Detour via frontage road to on-ramp at Montopolis Dr.

LANE CLOSURE — 5/3/21 to 5/5/21 — PAVING
Monday-Tuesday (5/3-5/4) 8 p.m. to 6 a.m., US 183 northbound mainlane will be reduced to one lane from Manor Springdale Rd. to US 290

RAMP CLOSURE — 5/3/21 to 5/4/21 — PAVING
Monday (5/3) 8 p.m. to 6 a.m., US 183 northbound exit ramp to US 290 frontage road will be closed. Detour via Cameron Rd. U-turn.

RAMP CLOSURE — 5/3/21 to 5/4/21 — PAVING
Monday (5/3) 8 p.m. to 6 a.m., US 183 northbound to US 290 westbound direct-connector will be closed. Detour via Cameron Rd.

RAMP CLOSURE — 5/3/21 to 5/4/21 — UTILITY WORK
Monday (5/3) 8 p.m. to 6 a.m., SH 71 westbound right two mainlanes will be closed from Spirit of Texas to US 183.

LANE CLOSURE — 5/3/21 to 5/6/21 — GUARDRAIL WORK

Monday-Wednesday (5/3-5/5) 8 p.m. to 6 a.m., US 183 southbound on-ramp will be reduced to one lane from Vargas to Patton Ave.

LANE CLOSURE — 5/4/21 to 5/4/21 — INTERSECTION WORK
Tuesday (5/4) 9 a.m. to 3 p.m., Loyola westbound right lane will be closed at US 183.

LANE CLOSURE — 5/4/21 to 5/5/21 — SIGN INSTALLATION
Tuesday-Wednesday (5/4-5/5) 9 a.m. to 3 p.m., westbound SH 71 left mainlane will be closed from US 183 to E. Riverside Dr.

LANE CLOSURE — 5/4/21 to 5/6/21 — PAVING
Tuesday-Wednesday (5/4-5/5) 8 p.m. to 6 a.m., Access to US 183 will be closed from 7th St, 1st St, and Cesar Chavez eastbound. Detour via Levander Loop to US 183 southbound.

LANE CLOSURE — 5/4/21 to 5/6/21 — PAVING
Tuesday-Wednesday (5/4-5/5) 8 p.m. to 6 a.m., US 183 northbound mainlane will be reduced to one lane from Techni Center to Loyola.

RAMP CLOSURE — 5/4/21 to 5/5/21 — UTILITY WORK
Tuesday (5/4) 8 p.m. to 6 a.m., southbound US 183 to eastbound SH 71 will be reduced to one lane.

RAMP CLOSURE — 5/5/21 to 5/7/21 — BRIDGE CONSTRUCTION
Wednesday-Friday (5/5-5/7) 9 a.m. to 3 p.m., US 183 southbound right mainlane will be closed from Hudson to Thurgood Ave.

RAMP CLOSURE — 5/5/21 to 5/7/21 — PAVING
Wednesday-Thursday (5/5-5/6) 8 p.m. to 6 a.m., westbound SH 71 to US 183 northbound will be closed at SH 71. Detour via E. Riverside Dr. U-turn to US 183 north cloverleaf.

RAMP CLOSURE — 5/5/21 to 5/7/21 — PAVING

Wednesday-Thursday (5/5-5/6) 8 p.m. to 6 a.m., US 183 northbound mainlane will be reduced to one lane from Loyola to US 290.

RAMP CLOSURE — 5/5/21 to 5/7/21 — UTILITY WORK

Wednesday-Thursday (5/5-5/6) 8 p.m. to 6 a.m., Levander Loop will be closed at Cesar Chavez and at US 183 northbound. Detour via Shady Lane to Cesar Chavez, to southbound US 183 ramp to U-turn at Montopolis Dr.

RAMP CLOSURE — 5/10/21 to 5/11/21 — PAVING

Monday (5/10) 8 p.m. to 6 a.m., northbound US 183 to eastbound SH 71 towards Austin Airport will be closed. Detour westbound SH 71 to E. Riverside Dr. U-turn to access eastbound SH 71, and north US 183 mainlanes will be reduced to one lane from E. Riverside Dr. to SH 71.

 


.

Long Term

• NONE AT THIS TIME •

 

Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.