ERCOT Board Approves Transmission Project In West Texas

Between 2010 and 2016, the average load growth in Far West Texas was about eight percent. An increase in the number of generation projects, mostly solar, being developed in this region is also a factor.

AUSTIN, TX– The ERCOT Board of Directors has endorsed a transmission project that includes two new 345-kV lines to help address future reliability concerns in the growing region of Far West Texas.

“We continue to see a tremendous amount of load growth in West Texas,” said ERCOT Senior Manager of Transmission Planning Jeff Billo. “Based on projected load growth in this area, these new lines will be needed to support system reliability in the coming years.”

Increased oil and natural gas exploration in the Permian Basin area in Far West Texas has contributed to high load growth in the region. Between 2010 and 2016, the average load growth in Far West Texas was about eight percent. An increase in the number of generation projects, mostly solar, being developed in this region is also a factor.

The new high voltage power lines will be built by transmission service providers Oncor, American Electric Power Service Corporation (AEPSC) and the Lower Colorado River Authority Transmission Services Corporation. Oncor and AEPSC initially proposed the project to the ERCOT Regional Planning Group in April 2016.

An independent analysis performed by ERCOT confirmed the project’s necessity. ERCOT analyzed more than 40 options and proposed the most cost-effective option to meet reliability needs in the area.

The project will include a new, 345-kV transmission line that will connect the Odessa and Riverton substations. It will span approximately 101 miles across Ector, Winkler, Loving and Reeves counties. In this area alone, peak electricity demand has jumped from 22 MW in 2010 to more than 200 MW in 2016. It is projected to exceed 500 MW by 2021.

The second new, 345-kW transmission line will be located further south in Pecos County, spanning about 68 miles and connecting the Bakersfield and Solstice substations.

The estimated capital cost for these improvements is $336 million. ERCOT estimates the project will be completed in the next four to five years, pending approval from the Public Utility Commission of Texas. 


 

Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.