TxDOT knows you’ve got to get where you need to go.
While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.
35 CORRIDOR MOBILITY CAPITAL AREA
Closures, Detours, Traffic Alerts
for January 18 – 24
Z
I-35 AT POSEY ROAD
PROJECT OVERVIEW | This project will construct a new overpass on I-35 over Posey Road, add two new U-turns in each direction at Posey Road, perform ramp reversals and convert two-way frontage roads to one-way.
Currently, the I-35 mainlanes go under Posey Road. The new configuration will have the I-35 mainlanes going over Posey Road.
• THIS WEEK’S PROJECT TRAFFIC ADVISORY•
Closures are weather permitting
- Posey Road bridge closed at I-35. | Until further notice
- Northbound I-35 exit #199 for Posey Road and exit #200 for Centerpoint Road are closed. | Until further notice
Read more on construction phasing and additional project details HERE.
I-35 FROM STASSNEY LANE TO WILLIAM CANNON DRIVE
PROJECT OVERVIEW | The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek.
New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 mainlanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.
Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.
•
- Southbound I-35 frontage road left lane closed from Battle Bend Boulevard to Stassney Lane. | Saturday, Jan. 18 from 7 AM until 3 PM
- Northbound I-35 frontage road left two lanes closed daily at Stassney Lane. | Monday, Jan. 20 through Tuesday, Jan. 21 from 9 AM until 3 PM
- Southbound and eastbound I-35 right lane closed daily at Stassney Lane. | Monday, Jan. 20 through Wednesday, Jan. 22 from 9 AM until 3 PM
- Southbound I-35 frontage road left lane closed at Stassney Lane. | Monday, Jan. 20 from 9 AM until 3 PM
- Southbound I-35 frontage road left lane closed at Stassney Lane. | Tuesday, Jan. 21 from 9 AM until 3 PM
- Northbound I-35 left lane closed from Onion Creek to Brandt Road. | Wednesday, Jan. 22 from 9 PM until 5 AM
- Northbound I-35 left lane closed from Brandt Road to William Cannon Drive. | Thursday, Jan. 23 from 9 PM until 5 AM
- East and westbound Stassney Lane left lane closed daily at I-35. | Thursday, Jan. 23 through Friday, Jan. 24 from 9 AM until 3 PM
Read more on construction phasing and additional project details HERE.
I-35 AT OLTORF ST.
PROJECT OVERVIEW | Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads.
Additionally, construction of new extended entrance/exit lanes for mainlanes and ramps, and adding U-turns in both directions at Oltorf Street.
Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.
- Northbound I-35 frontage road left lane closed from Woodward Street to Oltorf Street. | Until further notice
- Southbound I-35 right two lanes closed from Woodland Avenue to Woodward Street. | Monday, Jan. 20 from 10 PM until 6 AM
- Northbound I-35 right two lanes closed from Woodward Street to Woodland Avenue. | Tuesday, Jan. 21 from 10 PM until 5 AM
Read more on construction phasing and additional project details HERE.
I-35 FROM RUNDBERG LN. TO US 290 EAST
PROJECT OVERVIEW |This project includes main-lanes and frontage road reconstruction and the addition of three new flyovers at US 183.
The project also includes reconstruction of the St. Johns Avenue Bridge, the addition of frontage road U-turns on both sides, intersection bypass lanes under St. Johns Avenue in both directions, extended entrance/exit lanes, and ramp and shoulder improvements.
• THIS WEEK’S PROJECT TRAFFIC ADVISORY •
Closures are weather permitting
- Northbound I-35 frontage road left lane closed from Camino La Costa to St. Johns Avenue. | Through mid-2020
- Northbound US 183 frontage road left lane closed from I-35 to Gessner Drive. | Through mid-2020
- Northbound US 183 frontage road reduced to one lane nightly from Cameron Road to I-35. The Cameron Road entrance and exit ramps will also be closed. | Sunday, Jan. 19 through Thursday, Jan. 23 from 9 PM until 5 AM
- Southbound I-35 reduced to one lane nightly from Rundberg Lane to US 290 East. The northbound US 183 flyover and the southbound Rundberg Lane entrance and exit ramps will also be closed. | Sunday, Jan. 19 through Thursday, Jan. 23 from 9 PM until 5 AM
- Northbound I-35 reduced to one lane nightly from US 290 East to Rundberg Lane. The northbound US 183 flyover and southbound US 290 East entrance and exit ramps will also be closed along with Exit #240 and Exit #241. | Sunday, Jan. 19 through Thursday, Jan. 23 from 10 PM until 5 AM
- Southbound I-35 frontage road reduced to one lane nightly from Rundberg Lane to Barwood Park. The St. Johns Avenue exit ramp will also be closed. | Sunday, Jan. 19 through Tuesday, Jan. 21 from 10 PM until 5 AM
- Southbound US 183 frontage road left lane closed from Carver Avenue to Cameron Road. The exit ramp will also be closed. | Sunday, Jan. 19 through Thursday, Jan. 23 from 9 PM until 5 AM
- East and westbound US 183 closed at Norwood Park Boulevard. | Until further notice
- East and westbound I-35 closed at Hermitage Drive. | Until further notice
Read more on construction phasing and additional project details HERE.
I-35 FROM 1431 TO FM 3406 (NORTHBOUND)
PROJECT OVERVIEW |The intersection of FM 3406 and the I-35 frontage roads are being improved, and the FM 3406 bridge over I-35 is being reconstructed.
The FM 3406 (Old Settlers Blvd) bridge will close to eastbound traffic. Westbound traffic will detour to the newly constructed U-turn Bridge.
•THIS WEEK’S PROJECT TRAFFIC ADVISORY•
Closures are weather permitting
- Northbound I-35 frontage road reduced to one lane from Jeffrey Way to RM 1431. | Through late 2020
Read more on construction phasing and additional project details HERE.
I-35 FROM US 79 TO SH 45 NORTH
PROJECT ACTIVITY | New braided ramps (where one ramp crosses over the other) are being constructed along the northbound I-35 mainlanes between Hesters Crossing and RM 620 to eliminate merging conflicts.
•
• NONE AT THIS TIME •
Closures are weather permitting
•
Read more on construction phasing and additional project details HERE.
I-35 AT PARMER LANE
PROJECT OVERVIEW | Reduced congestion, improved mobility at Parmer Lane and Lamar Boulevard, operational efficiency, more reliable travel times, lower fuel consumption. The start date is summer 2019 and is scheduled to be completed summer of 2021. The construction costs are estimated to be $24.6 million.
•
•THIS WEEK’S PROJECT TRAFFIC ADVISORY•
Closures are weather permitting
- Southbound I-35 frontage road closed from Parmer Lane to Yager Lane. The Parmer Lane entrance ramp will also be closed. | Thursday, Jan. 23 from 9 PM until 5 AM
- Southbound I-35 right lane closed from Parmer Lane to Yager Lane. | Thursday, Jan. 23 from 9 PM until 5 AM
Read more on construction phasing and additional project details HERE.
I-35 CORRIDOR MAINTENANCE CLOSURES & DETOURS
PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor.
•
• THIS WEEK’S PROJECT TRAFFIC ADVISORY •
Closures are weather permitting
•
- Northbound I-35 left lane closed from State Spur 26 (S. Austin Ave) to SH 29. | Monday, Jan. 20 from 10 PM until 5 AM
- Northbound I-35 left lane closed from North Fork (San Gabriel River) to Lakeway Drive. | Tuesday, Jan. 21 from 10 PM until 5 AM
- Southbound I-35 frontage road right lane closed from 50th Street to 49th Street. | Saturday, Jan. 18 from 7 AM until 7 PM
- Northbound I-35 left lane closed from the Hays County line to Onion Creek. | Tuesday, Jan. 21 from 9 PM until 5 AM
- Northbound I-35 left lane closed from Goforth Road to the Travis County line. | Monday, Jan. 20 from 9 PM until 5 AM
Read more on construction phasing and additional project details HERE.