I-35 Weekly Closures & Detour Alerts

TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.

35 CORRIDOR MOBILITY CAPITAL AREA

Closures, Detours, Traffic Alerts

for January 11 – 17

Z

I-35 AT POSEY ROAD

PROJECT OVERVIEW | This project will construct a new overpass on I-35 over Posey Road, add two new U-turns in each direction at Posey Road, perform ramp reversals and convert two-way frontage roads to one-way.

Currently, the I-35 mainlanes go under Posey Road. The new configuration will have the I-35 mainlanes going over Posey Road.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

 

  • Posey Road bridge closed at I-35. | Until further notice

 

  • Northbound I-35 exit #199 for Posey Road and exit #200 for Centerpoint Road are closed. | Until further notice

 

  • Northbound I-35 frontage road left lane closed at Posey Road. | Monday, Jan. 13 from 9 PM until 5 AM

 

  • Northbound I-35 frontage road left lane closed from York Creek Road to Posey Road. | Tuesday, Jan. 14 from 9 PM until 5 AM

 

  • East and westbound Posey Road left lane closed at the I-35 frontage road. | Tuesday, Jan. 14 through Wednesday Jan. 15 from 9 PM until 5 AM

 

  • Northbound I-35 frontage road left lane closed from York Creek Road to Posey Road. | Thursday, Jan. 16 from 9 PM until 5 AM

Read more on construction phasing and additional project details HERE.

 

I-35 FROM STASSNEY LANE TO WILLIAM CANNON DRIVE

PROJECT OVERVIEW | The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 mainlanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.

Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 AT OLTORF ST.

PROJECT OVERVIEW | Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads.

Additionally, construction of new extended entrance/exit lanes for mainlanes and ramps, and adding U-turns in both directions at Oltorf Street.

Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 FROM RUNDBERG LN. TO US 290 EAST

PROJECT OVERVIEW | This project includes main-lanes and frontage road reconstruction and the addition of three new flyovers at US 183.

The project also includes reconstruction of the St. Johns Avenue Bridge, the addition of frontage road U-turns on both sides, intersection bypass lanes under St. Johns Avenue in both directions, extended entrance/exit lanes, and ramp and shoulder improvements.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 frontage road left lane closed from Camino La Costa to St. Johns Avenue. | Through mid-2020

 

  • Northbound US 183 frontage road left lane closed from I-35 to Gessner Drive. | Through mid-2020

 

  • Northbound US 183 frontage road right lane closed nightly from Norwood Park Boulevard to Clock Tower Drive. | Tuesday, Jan. 7 through Thursday, Jan. 16 from 9 PM until 5 AM

 

  • Southbound I-35 frontage road right lane closed daily from Blackson Avenue to St. Johns Avenue. | Saturday, Jan. 11 through Monday, Jan. 13 from 9 AM until 3 PM

 

  • Southbound I-35 frontage road left lane closed nightly from Carver Avenue to Cameron Road. The Cameron Road exit ramp will also be closed. | Sunday, Jan. 12 through Thursday, Jan. 16 from 9 PM until 5 AM

 

  • Northbound US 183 right lane closed nightly from Cameron Road to I-35. The Cameron Road entrance ramp will also be closed. | Sunday, Jan. 12 through Thursday, Jan. 16 from 9 PM until 5 AM

 

  • Southbound I-35 frontage road right lane closed nightly from Barwood Park to Powell Lane. | Sunday, Jan. 12 through Tuesday, Jan. 14 from 9 PM until 5 AM

 

  • Northbound I-35 right two lanes closed nightly from Rutherford Lane to Rundberg Lane. | Sunday, Jan. 12 through Tuesday, Jan. 14 from 9 PM until 5 AM

 

  • Southbound I-35 right two lanes closed nightly from US 183 to US 290 East. The northbound US 183 flyover and US 290 East exit ramp will also be closed. | Sunday, Jan. 12 through Thursday, Jan. 16 from 10 PM until 5 AM

 

  • Northbound I-35 right two lanes closed nightly from US 290 East to US 183. The northbound US 183 flyover and the southbound US 290 East exit ramp will also be closed. | Sunday, Jan. 12 through Thursday, Jan. 16 from 10 PM until 5 AM

 

  • North and southbound I-35 left two lanes closed nightly from US 183 to Hermitage Drive. | Sunday, Jan. 12 through Thursday, Jan. 16 from 9 PM until 5 AM

 

  • Northbound I-35 frontage road right lane closed nightly from Blackson Avenue to US 183. | Monday, Jan. 13 through Tuesday, Jan. 14 from 9 PM until 5 AM

Read more on construction phasing and additional project details HERE.

I-35 FROM 1431 TO FM 3406 (NORTHBOUND)

PROJECT OVERVIEW | The intersection of FM 3406 and the I-35 frontage roads are being improved, and the FM 3406 bridge over I-35 is being reconstructed.

The FM 3406 (Old Settlers Blvd) bridge will close to eastbound traffic. Westbound traffic will detour to the newly constructed U-turn Bridge.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

 

  • Northbound I-35 frontage road reduced to one lane from FM 3406 (Old Settlers Boulevard) to RM 1431 (University Boulevard). | Through late 2020

Read more on construction phasing and additional project details HERE.

I-35 FROM US 79 TO SH 45 NORTH

PROJECT ACTIVITY | New braided ramps (where one ramp crosses over the other) are being constructed along the northbound I-35 mainlanes between Hesters Crossing and RM 620 to eliminate merging conflicts.

NONE AT THIS TIME

Closures are weather permitting

Read more on construction phasing and additional project details HERE.

I-35 AT PARMER LANE

PROJECT OVERVIEW | Reduced congestion, improved mobility at Parmer Lane and Lamar Boulevard, operational efficiency, more reliable travel times, lower fuel consumption. The start date is summer 2019 and is scheduled to be completed summer of 2021. The construction costs are estimated to be $24.6 million.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Southbound I-35 frontage road left lane closed daily at Parmer Lane. | Through early 2020

Read more on construction phasing and additional project details HERE.

I-35 CORRIDOR MAINTENANCE CLOSURES & DETOURS

PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Southbound I-35 frontage road right lane closed from 50th Street to 49th Street. | Saturday, Jan. 18 from 7 AM until 7 PM

 

  • Southbound I-35 exit ramp closed at 15th Street. | Sunday, Jan. 12 from 9 PM until 12 AM

 

  • Northbound I-35 left lane closed from Onion Creek Parkway to the William Cannon Drive exit ramp. | Wednesday, Jan. 15 from 9 PM until 5 AM

 

  • Northbound I-35 left lane closed from Brandt Road to Boggy Creek Drive. | Thursday, Jan. 16 from 9 PM until 5 AM

 

  • Northbound I-35 left lane closed from FM 1327 to Onion Creek Parkway. | Tuesday, Jan. 14 from 9 PM until 5 AM

 

  • Northbound I-35 left lane closed from Main Street to FM 1327. | Tuesday, Jan. 14 from 9 PM until 5 AM

 

  • Northbound I-35 left lane closed from Hillside Terrace to Main Street. | Monday, Jan. 13 from 9 PM until 5 AM

 

  • Southbound I-35 frontage road left lane closed daily at Park 35 Circle. | Tuesday, Jan. 14 through Thursday, Jan. 16 from 9 AM until 4 PM

 

  • Northbound I-35 left lane closed from Westinghouse Road to Leander Road. | Monday, Jan. 13 from 10 PM until 5 AM

 

  • Northbound I-35 left lane closed from Robert S. Light Boulevard to North Turnersville Road. | Monday, Jan. 13 from 9 PM until 5 AM

Read more on construction phasing and additional project details HERE.


Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.