While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.
Remember to support your local businesses as they are still open during construction…
.
………………CLOSURES, DETOURS & TRAFFIC ALERTS
.
………………FEBRUARY 6 — FEBRUARY 12, 2021
.
Currently, the I-35 main lanes go under Posey Road. With the new configuration, I-35 main lanes will be going over Posey Road.
This project is made possible by a partnership between Hays County/TxDOT and is expected to cost $31.7 million funded by TxDOT.
The I-35 and Posey Road construction started in February 2019, and anticipated construction completion is planned for mid-2021. The project contractor is Webber, LLC.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 Posey Road exit (#199) closed.
• Until further notice.
Read more on construction phasing and additional project details HERE.
The estimated construction cost is $21.9 million and is funded by the Capital Area Metropolitan Planning Organization (CAMPO) and TxDOT. Construction commenced in September 2020, and its anticipated completion is early 2022. Hunter Industries, Ltd is the contractor for this project.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 frontage road right lane closed from FM 1626 to Kyle Crossing.
• Through late 2021.
Read more on construction phasing and additional project details HERE.
New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive. The I-35 main lanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for a smoother merge onto I-35.
This major project is estimated to cost $78.8 million. Construction started in July 2016, with the anticipated completion in late 2020. The contractor for this project is OHL, USA, Inc.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 frontage road right lane closed from the William Cannon Drive exit (#228) to Boggy Creek Drive.
• Monday, Feb. 8 from 9 a.m. until 3 p.m.
Southbound I-35 frontage road right lane closed from William Cannon Drive to Corral Lane.
• Monday, Feb. 8 from 9 a.m. until 3 p.m.
Southbound I-35 frontage road left lane closed at Stassney Lane.
• Tuesday, Feb. 9 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
I-35 from Rundberg Lane to US 290 East is estimated to cost $124.2 million and is made possible by Texas Clear Lanes Congestion Relief Fund.
The construction commenced in January 2018, with an anticipated completion date in mid-2021. The contractor for this project is J.D. Abrams.
.
All closures are weather permitting.
.
• CURRENT TRAFFIC ADVISORIES •
Southbound to northbound I-35 U-turn closed continuously at US 183.
• Through Friday, Feb. 12 at 3 p.m.
Northbound US 183 frontage road reduced to one lane from I-35 to Gessner Drive.
• Through February 2021.
Northbound to southbound I-35 U-turn closed at Rundberg Lane.
• Through October 2021.
Northbound and southbound I-35 left two lanes closed nightly from Norwood Park Boulevard to US 183.
• Monday, Feb. 8 through Thursday, Feb. 11 from 9 p.m. until 5 a.m.
Northbound US 183 frontage road left lane closed nightly from Norwood Park Boulevard to Clock Tower Drive.
• Monday, Feb. 8 through Thursday, Feb. 11 from 9 p.m. until 5 a.m.
Northbound I-35 to northbound US 183 flyover closed continuously.
• Friday, Feb. 12 from 9 p.m. through Sunday, Feb. 14 until 11 a.m.
Northbound US 183 reduced to one lane continuously.
• Friday, Feb. 12 from 9 p.m. through Sunday, Feb. 14 until 11 a.m.
Read more on construction phasing and additional project details HERE.
This project’s estimated construction cost is funded by Texas Clear Lanes and Capital Area Metropolitan Planning Organization (CAMPO) with an estimated $24.6 million cost.
Construction started in July 2019 with an estimated timeline to be completed by mid-2021. Primoris Services Corporation is the project contractor.
All closures are weather permitting.
.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 bypass lane closed at Parmer Lane.
• Through early 2021.
Northbound I-35 frontage road left two lanes closed at Parmer Lane.
• Monday, Feb. 10 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
The projected cost is estimated at $8.2 million and funded by CAMPO and TxDOT. Construction will start in August 2020 and is anticipated to be complete in mid-2021. The project contractor is Jordan Foster Construction.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 right lane closed at Grand Avenue Parkway. The Grand Avenue Parkway entrance ramp will also be closed.
• Sunday, Feb. 7 from 11 p.m. until 6 a.m.
Read more on construction phasing and additional project details HERE.
PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor.
All closures are weather permitting.
Northbound and southbound I-35 rolling closures nightly from Williams Drive to SH 130 for LCRA transmission line installation.
• Through Sunday, Feb. 28 from 9 p.m. until 5 a.m.
Northbound and southbound I-35 frontage road left lane closed from Louis Henna Boulevard to Howard Lane.
• Monday, Feb. 8 from 9 a.m. until 3 p.m.
Northbound I-35 frontage road left lane closed nightly from Park Plaza Drive to Rundberg Lane.
• Monday, Feb. 8 through Thursday, Feb. 11 from 9 p.m. until 5 a.m.
Northbound and southbound I-35 frontage road left lane closed from Wells Branch Parkway to Tech Ridge Boulevard.
• Tuesday, Feb. 9 from 9 a.m. until 3 p.m.
Northbound and southbound I-35 frontage road left lane closed from Howard Lane to Braker Lane.
• Wednesday, Feb. 10 from 9 a.m. until 3 p.m.
Northbound I-35 frontage road left lane closed from 38 1/2 Street to Dean Keeton Street. The Dean Keeton Street exit (#236) will also be closed.
• Wednesday, Feb. 10 from 10 p.m. until 5 a.m.
Northbound and southbound I-35 frontage road left lane closed from Tech Ridge Boulevard to Rundberg Lane.
• Thursday, Feb. 11 from 9 a.m. until 3 p.m.
Northbound and southbound I-35 frontage road left lane closed from Braker Lane to US 183.
• Friday, Feb. 12 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…
The San Marcos River Rollers have skated through obstacles after taking a two-year break during…
San Marcos Corridor News has been reporting on the incredible communities in the Hays County…
Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…
Looking to adopt or foster animals from the local shelter? Here are the San Marcos…
The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…
This website uses cookies.