Staff
While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.
Remember to support your local businesses as they are still open during construction…
.
………………CLOSURES, DETOURS & TRAFFIC ALERTS
.
………………MARCH 13 — MARCH 19, 2021
.
Currently, the I-35 main lanes go under Posey Road. With the new configuration, I-35 main lanes will be going over Posey Road.
This project is made possible by a partnership between Hays County/TxDOT and is expected to cost $31.7 million funded by TxDOT.
The I-35 and Posey Road construction started in February 2019, and anticipated construction completion is planned for mid-2021. The project contractor is Webber, LLC.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Eastbound and westbound Posey Road closed at I-35 frontage road.
• Until further notice.
Northbound I-35 Posey Road exit (#199) closed.
• Until further notice.
Read more on construction phasing and additional project details HERE.
The estimated construction cost is $21.9 million and is funded by the CAMPO and TxDOT. Construction commenced in September 2020, and its anticipated completion is early 2022. Hunter Industries, Ltd is the contractor for this project.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 frontage road right lane closed from FM 1626 to Kyle Crossing.
• Through late 2021.
Read more on construction phasing and additional project details HERE.
The estimated construction cost is $14 million funded by CAMPO and TxDOT. Construction commenced in January 2021, and its anticipated completion in mid-2022i. Hunter Industries, Ltd is the contractor for this project.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
.
Northbound I-35 reduced to one lane from Aquarena Springs Drive to River Ridge Parkway.
• Sunday, March 14 from 9 p.m. until 5 a.m.
Northbound I-35 reduced to one lane from Aquarena Springs Drive to River Ridge Parkway.
• Sunday, March 14 from 9 p.m. until 5 a.m.
Northbound I-35 reduced to one lane from Aquarena Springs Drive to River Ridge Parkway.
• Monday, March 15 from 9 p.m. until 5 a.m.
Read more on construction phasing and additional project details HERE.
New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive. The I-35 main lanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for a smoother merge onto I-35.
This major project is estimated to cost $78.8 million. Construction started in July 2016, with the anticipated completion in late 2020. The contractor for this project is OHL, USA, Inc.
..All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Southbound I-35 left lane closed nightly at William Cannon Drive.
• Sunday, March 14 through Tuesday, March 16 from 9 p.m. until 5 a.m.
Southbound I-35 right lane closed from the Slaughter Lane exit to Slaughter Lane.
• Tuesday, March 16 through Wednesday, March 17 from 9 p.m. until 5 a.m.
Southbound I-35 right lane closed nightly at William Cannon Drive.
• Wednesday, March 17 through Thursday, March 18 from 9 p.m. until 5 a.m.
Southbound I-35 right lane closed at Slaughter Lane.
• Thursday, March 18 from 9 p.m. until 5 a.m.
Read more on construction phasing and additional project details HERE.
I-35 from Rundberg Lane to US 290 East is estimated to cost $124.2 million and is made possible by Texas Clear Lanes Congestion Relief Fund.
The construction commenced in January 2018, with an anticipated completion date in mid-2021. The contractor for this project is J.D. Abrams.
.
All closures are weather permitting.
.
• CURRENT TRAFFIC ADVISORIES •
Northbound to southbound I-35 U-turn closed continuously at Rundberg Lane.
• Through October 2021.
Southbound I-35 right lane closed nightly from St. Johns Avenue to US 290 East. The US 290 East exit (#238) will also be closed.
• Sunday, March 14 through Monday, March 15 from 9 p.m. until 5 a.m.
Northbound I-35 frontage road closed from US 183 to Norwood Park Boulevard.
• Monday, March 15 through Tuesday, March 16 from 9 p.m. until 5 a.m.
Northbound US 183 frontage road left lane closed from Norwood Park Boulevard to Clock Tower Drive. The Norwood Park Boulevard entrance ramp will also be closed.
• Monday, March 15 through Thursday, March 18 from 9 p.m. until 5 a.m.
Northbound US 183 frontage road closed nightly from Norwood Park Boulevard to Clock Tower Drive. The I-35/Lamar Boulevard exit will also be closed.
• Tuesday, March 16 through Thursday, March 18 from 9 p.m. until 5 a.m.
Read more on construction phasing and additional project details HERE.
This project’s estimated construction cost is funded by Texas Clear Lanes and CAMPO with an estimated $24.6 million cost.
Construction started in July 2019 with an estimated timeline to be completed by mid-2021. Primoris Services Corporation is the project contractor.
All closures are weather permitting.
.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 bypass lane closed at Parmer Lane.
• Through early 2021.
Southbound I-35 frontage road right-turn lane closed daily at Parmer Lane.
• Monday, March 15 through Wednesday, March 17 from 9 a.m. until 3 p.m.
Westbound Howard Lane right lane closed daily at I-35.
• Monday, March 15 through Wednesday, March 17 from 9 a.m. until 3 p.m.
Southbound I-35 reduced to one lane nightly from Parmer Lane to Braker Lane. The Braker Lane exit (#243) will also be closed.
• Tuesday, March 16 through Wednesday, March 17 from 9 p.m. until 5 a.m.
Southbound I-35 frontage road right lane closed daily at Howard Lane.
• Tuesday, March 16 through Friday, March 19 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
The projected cost is estimated at $8.2 million and funded by CAMPO and TxDOT. Construction will start in August 2020 and is anticipated to be complete in mid-2021. The project contractor is Jordan Foster Construction.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
…..NONE AT THIS TIME
Read more on construction phasing and additional project details HERE.
PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 right lane closed from 8th Street to 11th Street.
• Sunday, March 14 from 10 p.m. until 5 a.m.
Southbound I-35 right two lanes closed nightly from 51st Street to Airport Boulevard. The 46th Street entrance ramp will also be closed.
• Monday, March 15 through Thursday, March 18 from 10 p.m. until 4 a.m.
Northbound I-35 Conrads Lane/Kohlenberg Road entrance ramp closed permanently.
• Tuesday, March 16.
Southbound I-35 frontage road right lane closed at Colonial Park Boulevard.
• Friday, March 19 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…
The San Marcos River Rollers have skated through obstacles after taking a two-year break during…
San Marcos Corridor News has been reporting on the incredible communities in the Hays County…
Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…
Looking to adopt or foster animals from the local shelter? Here are the San Marcos…
The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…
This website uses cookies.