Kyle, San Marcos, Austin I-35 road construction projects for week of July 24

Staff

TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do
everything it can to minimize disruptions.

Remember to support your local businesses as they are still open during construction…

I-35 CAPITAL AREA CORRIDOR MOBILITY

.

.

*LONG TERM CLOSURE: SPECIAL TRAFFIC ALERT

On Sunday, April 25 at 10 p.m., the existing northbound I-35 to northbound US 183 flyover will close to traffic, weather permitting.

During the closure, crews will demolish and reconstruct a portion of the flyover. Construction is expected to last approximately four months.

To accommodate this reconstruction, a long-term detour will be put in place.

Northbound I-35 drivers wishing to access northbound US 183 will use the Rundberg Lane exit (#241) and take the non-signalized U-turn at Rundberg Lane to access the new southbound I-35 to northbound US 183 flyover.

 

 

 

 

 

• CLOSURES, DETOURS & TRAFFIC ALERTS •

SATURDAY, JULY 24 — FRIDAY, JULY 30, 2021

.

I-35 AT POSEY ROAD

PROJECT OVERVIEW | This project will construct a new overpass on I-35 over Posey Road, add two new U-turns in each direction at Posey Road, perform ramp reversals and convert two-way frontage roads to one-way.

Currently, the I-35 main lanes go under Posey Road. With the new configuration, I-35 main lanes will be going over Posey Road.

This project is made possible by a partnership between Hays County/TxDOT and is expected to cost $31.7 million funded by TxDOT.

The I-35 and Posey Road construction started in February 2019, and anticipated construction completion is planned for mid-2021. The project contractor is Webber, LLC.

All closures are weather permitting.

CURRENT TRAFFIC ADVISORIES

LANE CLOSURE

Eastbound and westbound Posey Road closed at the I-35 frontage road.
Until further notice.

Read more on construction phasing and additional project details HERE.

.

.

I-35 FROM RM 150 TO KYLE CROSSING

PROJECT OVERVIEW | This project will reconfigure the northbound entrance/exit ramps between RM 150 and Kyle Crossing. The improvements include reversing the northbound entrance/exit ramps, reconstructing the northbound frontage road, adding new extended lanes between entrance/exit ramps, and constructing a new frontage road bridge over Plum Creek.

The estimated construction cost is $21.9 million and is funded by the CAMPO and TxDOT. Construction commenced in September 2020, and its anticipated completion is early 2022. Hunter Industries, Ltd is the contractor for this project.

All closures are weather permitting.

CURRENT TRAFFIC ADVISORIES

LANE CLOSURE

Northbound I-35 frontage road right lane closed from FM 1626 to Kyle Crossing.
Through late 2021.

Read more on construction phasing and additional project details HERE.

.

.

I-35 FROM SOUTH LOOP 82 TO NORTH
RIVER RIDGE PARKWAY

.
PROJECT
OVERVIEW | Work includes relocating the existing northbound I-35 entrance ramp, constructing a new northbound exit ramp, reconstructing the northbound frontage road, and adding a new extended entrance/exit lane.

The estimated construction cost is $14 million funded by CAMPO and TxDOT. Construction commenced in January 2021, and its anticipated completion in mid-2022. Hunter Industries, Ltd is the contractor for this project.
.

All closures are weather permitting.
.

NO CURRENT TRAFFIC ADVISORIES

Read more on construction phasing and additional project details HERE.

.

.

I-35 FROM STASSNEY TO WILLIAM CANNON DR

.
PROJECT
OVERVIEW |
The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive and the frontage road bridge over Williamson Creek. Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive. The I-35 main lanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for a smoother merge onto I-35.

This major project is estimated to cost $78.8 million. Construction started in July 2016, with the anticipated completion in late 2020. The contractor for this project is OHL, USA, Inc.

..All closures are weather permitting.

CURRENT TRAFFIC ADVISORIES

LANE CLOSURE

Northbound I-35 frontage road right lane closed at Boggy Creek Drive.
Saturday, July 24 from 9 a.m. until 3 p.m.

LANE CLOSURE

Northbound I-35 right lane closed from William Cannon Drive to the SH 71 / Ben White Boulevard exit (#231). The William Cannon Drive entrance ramp and the SH 71 / Ben White Boulevard exit will also be closed.
Sunday, July 25 from 9 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 right two lanes closed nightly from the Stassney Lane entrance ramp to the Slaughter Lane exit (#227).
Sunday, July 25 through Thursday, July 29 from 9 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 William Cannon Drive exit (#228) closed nightly.
Sunday, July 25 through Thursday, July 29 from 9 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 Stassney Lane entrance ramp closed nightly.
Sunday, July 25 through Thursday, July 29 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed daily from Slaughter Lane to SH 71/Ben White Boulevard.
Monday, July 26 through Tuesday, July 27 from 9 a.m. until 3 p.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed nightly from Stassney Lane to Teri Road Lane.
Tuesday, July 27 through Wednesday, July 28 from 9 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 frontage road left lane closed nightly from SH 71/Ben White Boulevard to Stassney Lane.
Tuesday, July 27 through Wednesday, July 28 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed at the William Cannon Drive. entrance ramp.
Tuesday, July 27 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 SH 71/Ben White Boulevard entrance ramp closed.
Wednesday, July 28 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 right lane closed at Slaughter Lane. The Slaughter Lane entrance ramp will also be closed.
Wednesday, July 28 from 9 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 right lane closed from SH 71/Ben White Boulevard to the Stassney Lane entrance ramp.
Wednesday, July 28 from 9 p.m. until 5 a.m.

Read more on construction phasing and additional project details HERE.

.

.

I-35 FROM RUNDBERG LN. TO US 290 EAST

.
PROJECT OVERVIEW |
This project includes main lanes and frontage road reconstruction and the addition of three new flyovers at US 183.

I-35 from Rundberg Lane to US 290 East is estimated to cost $124.2 million and is made possible by Texas Clear Lanes Congestion Relief Fund.

The construction commenced in January 2018, with an anticipated completion date in mid-2021. The contractor for this project is J.D. Abrams.

.
All closures are weather permitting.
.

CURRENT TRAFFIC ADVISORIES

LANE CLOSURE

Southbound I-35 US 183 exit (#240) closed.
Through fall 2021.

LANE CLOSURE

Northbound to southbound I-35 U-turn closed continuously at US 183.
Through fall 2021.

LANE CLOSURE

Northbound I-35 to northbound US 183 flyover closed continuously.
Through fall 2021.

LANE CLOSURE

Northbound to southbound I-35 U-turn closed continuously at Rundberg Lane.
Through fall 2021.

LANE CLOSURE

Northbound I-35 frontage road right lane closed from Blackson Avenue to US 183.
Saturday, July 24 from 6 a.m. until 11 a.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed nightly from US 290 East to US 183.
Sunday, July 25 through Friday, July 30 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed nightly from the Rundberg Lane exit (#241) to Park Plaza Drive.
Sunday, July 25 through Friday, July 30 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed nightly from US 183 to the Rundberg Lane exit (#241).
Sunday, July 25 through Friday, July 30 from 9 p.m. until 5 a.m.

LANE CLOSURE

Southbound US 183 right lane closed nightly from the Cameron Road exit to the Cameron Road entrance ramp.
Sunday, July 25 through Thursday, July 29 from 9 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed daily from US 290 East to US 183.
Monday, July 26 through Friday, July 30 from 9 a.m. until 3 p.m.

LANE CLOSURE

Northbound I-35 frontage road left lane closed daily from the Rundberg Lane exit (#241) to Hermitage Drive.
Monday, July 26 through Friday, July 30 from 9 a.m. until 3 p.m.

LANE CLOSURE

Southbound I-35 frontage road right lane closed daily at the Braker Lane entrance ramp.
Monday, July 26 through Tuesday, July 27 from 9 a.m. until 3 p.m.

LANE CLOSURE

Northbound I-35 closed from US 290 East to US 183.
Thursday, July 29 from 11 p.m. until 5 a.m.

Read more on construction phasing and additional project details HERE.

.

.

I-35 AT PARMER LANE

.
PROJECT
OVERVIEW |
Reduced congestion, improved mobility at Parmer Lane and Lamar Boulevard, operational efficiency, more reliable travel times, lower fuel consumption.

This project’s estimated construction cost is funded by Texas Clear Lanes and CAMPO with an estimated $24.6 million cost.

Construction started in July 2019 with an estimated timeline to be completed by mid-2021. Primoris Services Corporation is the project contractor.

All closures are weather permitting.

 

.

LANE CLOSURE

Northbound I-35 bypass lane closed at Parmer Lane.
Monday, July 26 from 9 a.m. until 3 p.m.

LANE CLOSURE

Southbound I-35 frontage road right lane closed daily at Yager Lane.
Monday, July 26 through Tuesday, July 27 from 9 a.m. until 3 p.m.

LANE CLOSURE

Eastbound Parmer Lane left lane closed at I-35.
Monday, July 26 from 8 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 frontage road right lane closed daily at Parmer Lane.
Wednesday, July 28 through Friday, July 30 from 9 a.m. until 3 p.m.

Read more on construction phasing and additional project details HERE.

.

.

I-35 FROM GRAND AVE PARKWAY TO SH-45 NORTH

.
PROJECT ACTIVITY |
Improvements include reversing ramps, constructing an extended entrance/exit lane on the northbound I-35 mainlanes under SH-45 North, along the frontage road, installing high-mast lighting, and improvements at Picadilly Drive and the I-35 frontage road.

The projected cost is estimated at $8.2 million and funded by CAMPO and TxDOT. Construction will start in August 2020 and is anticipated to be complete in mid-2021. The project contractor is Jordan Foster Construction.

All closures are weather permitting.

.

LANE CLOSURE

Northbound I-35 left lane closed nightly from Wells Branch Parkway to SH 45 North/Louis Henna Boulevard. The Wells Branch Parkway entrance ramp and the SH 45 North/Louis Henna Boulevard exit (#250) will also be closed.
Sunday, July 25 through Friday, July 30 from 9 p.m. until 5 a.m.

Read more on construction phasing and additional project details HERE.

.

.

I-35 CORRIDOR & HIGHWAY MAINTENANCE

.
PROJECT OVERVIEW
| These lane closures are associated with ongoing maintenance activities throughout the corridor.

All closures are weather permitting.

CURRENT TRAFFIC ADVISORIES

LANE CLOSURE

Northbound I-35 left lane closed nightly from the SH 123 exit (#204) to SH 80 exit (#205).
Monday, July 26 through Wednesday, July 28 from 10 p.m. until 5 a.m.

LANE CLOSURE

Northbound I-35 right lane closed from the Aquarena Springs Drive exit (#206) to SH 80.
Monday, July 26 from 10 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 left lane closed nightly from the Aquarena Springs Drive entrance ramp to the SH 123 exit (#204A).
Monday, July 26 through Wednesday, July 28 from 10 p.m. until 5 a.m.

LANE CLOSURE

Southbound I-35 right lane closed at Main Street.
Wednesday, July 28 from 10 p.m. until 5 a.m.

Read more on construction phasing and additional project details HERE.

.

Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.