While construction is tough on everyone, TxDOT is trying to do
everything it can to minimize disruptions.
Remember to support your local businesses as they are still open during construction…
.
.
Currently, the I-35 main lanes go under Posey Road. With the new configuration, I-35 main lanes will be going over Posey Road.
This project is made possible by a partnership between Hays County/TxDOT and is expected to cost $31.7 million funded by TxDOT.
The I-35 and Posey Road construction started in February 2019, and anticipated construction completion is planned for mid-2021. The project contractor is Webber, LLC.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound and southbound I-35 left lane closed nightly from Centerpoint Road to York Creek Road.
• Friday, Sept. 3 through Saturday, Sept. 18 from 9 p.m. until 5 a.m.
Read more on construction phasing and additional project details HERE.
TxDOT anticipates periodic closures of the river at I-35 to complete the work. Recreational users along the San Marcos River will be notified in advance of any closures via shore signs and can sign up for additional project updates
The estimated project cost is $107 million and is funded by CAMPO and TxDOT. Construction commenced in August 2021 and its anticipated completion in early 2025, weather permitting. Webber, LLC is the contractor for this project.
• NO CURRENT TRAFFIC ADVISORIES •
Read more on construction phasing and additional project details HERE.
The estimated construction cost is $21.9 million and is funded by the CAMPO and TxDOT. Construction commenced in September 2020, and its anticipated completion is early 2022. Hunter Industries, Ltd is the contractor for this project.
All closures are weather permitting.
.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 frontage road right lane closed from FM 1626 to Kyle Crossing.
• Through late 2021.
Read more on construction phasing and additional project details HERE.
.
PROJECT OVERVIEW | Work includes relocating the existing northbound I-35 entrance ramp, constructing a new northbound exit ramp, reconstructing the northbound frontage road, and adding a new extended entrance/exit lane.
The estimated construction cost is $14 million funded by CAMPO and TxDOT. Construction commenced in January 2021, and its anticipated completion in mid-2022. Hunter Industries, Ltd is the contractor for this project.
.
All closures are weather permitting.
.
• NO CURRENT TRAFFIC ADVISORIES •
Read more on construction phasing and additional project details HERE.
.
PROJECT OVERVIEW | The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive and the frontage road bridge over Williamson Creek. Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.
New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive. The I-35 main lanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for a smoother merge onto I-35.
This major project is estimated to cost $78.8 million. Construction started in July 2016, with the anticipated completion in late 2020. The contractor for this project is OHL, USA, Inc.
All closures are weather permitting.
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 frontage road right lane closed daily from Tranquilo Trail to Boggy Creek Drive.
• Tuesday, Sept. 7 through Saturday, Sept. 11 from 9 a.m. until 3 p.m.
Southbound I-35 frontage road left lane closed daily from Chaparral Road to Corral Lane.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Southbound I-35 Stassney Lane entrance ramp closed daily.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Southbound I-35 Slaughter Lane exit (#227) closed daily.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Northbound and southbound I-35 frontage road left lane closed daily at William Cannon Drive. The southbound to northbound I-35 U-turn will also be closed.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Northbound I-35 right lane closed daily at the Slaughter Lane entrance ramp. The Slaughter Lane entrance ramp will also be closed.
• Wednesday, Sept. 8 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Northbound I-35 frontage road left lane closed daily at William Cannon Drive. The northbound to southbound I-35 U-turn will also be closed.
• Wednesday, Sept. 8 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Northbound and southbound I-35 frontage road left lane closed daily at Stassney Lane. The northbound and southbound I-35 U-turns will also be closed.
• Wednesday, Sept. 8 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
PROJECT OVERVIEW | This project includes main lanes and frontage road reconstruction and the addition of three new flyovers at US 183.
I-35 from Rundberg Lane to US 290 East is estimated to cost $124.2 million and is made possible by Texas Clear Lanes Congestion Relief Fund.
The construction commenced in January 2018, with an anticipated completion date in mid-2021. The contractor for this project is J.D. Abrams.
.
All closures are weather permitting.
.
• CURRENT TRAFFIC ADVISORIES •
Southbound I-35 US 183 exit (#240) closed continuously.
• Through fall 2021.
Northbound to southbound I-35 U-turn closed continuously at Rundberg Lane.
• Through fall 2021.
Northbound I-35 frontage road right lane closed continuously from US 290 East to La Posada Drive.
• Through fall 2021.
Northbound I-35 to northbound US 183 flyover closed continuously.
• Through Saturday, Sept. 11, 2021 at 8 a.m.
Northbound I-35 left lane closed nightly from US 290 East to Rundberg Lane. The Rundberg Lane exit (#241) and US 290 East entrance ramp will also be closed.
• Tuesday, Sept. 7 through Thursday, Sept. 9 from 9 p.m. until 5 a.m.
Northbound US 183 left lane closed nightly from I-35 to Georgian Drive. The southbound I-35 to northbound US 183 flyover and the Georgian Drive entrance ramp will also be closed.
• Tuesday, Sept. 7 through Thursday, Sept. 9 from 9 p.m. until 5 a.m.
Northbound I-35 frontage road left lane closed nightly from US 290 East to US 183.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 p.m. until 5 a.m.
Northbound I-35 right two lanes closed nightly at Rundberg Lane. The Rundberg Lane entrance ramp will also be closed.
• Tuesday, Sept. 7 through Thursday, Sept. 9 from 9 p.m. until 5 a.m.
Southbound I-35 frontage road left lane closed daily from Park Plaza Drive to Powell Lane.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Northbound I-35 closed from the US 290 East entrance ramp to the Rundberg Lane exit (#241). The US 290 East entrance ramp and the Rundberg Lane exit will also be closed.
• Friday, Sept. 10 from 11 p.m. until 8 a.m.
Read more on construction phasing and additional project details HERE.
PROJECT OVERVIEW | Reduced congestion, improved mobility at Parmer Lane and Lamar Boulevard, operational efficiency, more reliable travel times, lower fuel consumption.
This project’s estimated construction cost is funded by Texas Clear Lanes and CAMPO with an estimated $24.6 million cost.
Construction started in July 2019 with an estimated timeline to be completed by mid-2021. Primoris Services Corporation is the project contractor.
All closures are weather permitting.
Northbound and southbound I-35 frontage road right lane closed daily at Parmer Lane.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Eastbound and westbound Parmer Lane left lane closed daily from Center Lake Drive to North Lamar Boulevard.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Westbound Parmer Lane right lane closed daily at the northbound I-35 frontage road.
• Tuesday, Sept. 7 through Friday, Sept. 10 from 9 a.m. until 3 p.m.
Read more on construction phasing and additional project details HERE.
.
PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor.
.
All closures are weather permitting.
..
• CURRENT TRAFFIC ADVISORIES •
Northbound I-35 right lane closed nightly from Wells Branch Parkway to SH 45/Louis Henna Boulevard. Multiple entrances and exit ramps will also be closed.
• Tuesday, Sept. 7 through Thursday, Sept. 9 from 9 p.m. until 4 a.m.
Read more on construction phasing and additional project details HERE.
The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…
The San Marcos River Rollers have skated through obstacles after taking a two-year break during…
San Marcos Corridor News has been reporting on the incredible communities in the Hays County…
Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…
Looking to adopt or foster animals from the local shelter? Here are the San Marcos…
The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…
This website uses cookies.