AQUARENA SPRINGS/THORPE/CHARLES AUSTIN: Aquarena Springs from Thorpe to Charles Austin will be reduced to one lane on each direction with partial sidewalk closures for construction project through end of March nightly. Charles Austin will be closed to through traffic at Aquarena Springs; City Park and the San Marcos Rec Hall can be accessed by turning from Hopkins. TxDOT, 512.619.4676.
120 E. SAN ANTONIO: The alley way between the Marc and Allstate will be closed to all traffic from 2 p.m. on March 3 through 2 a.m. on March 4, 2016. The Marc, 214.546.8473
ELLIS ST: All lanes in both directions will be closed for the installation of box culverts through the end of February. Smith Contracting, 512.694.2552
YARRINGTON RD: The two south bound  inside main lanes north and south of Yarrington will be closed on Feb. 28 – March 3 from 5 a.m. to 5 a.m. for bridge maintenance, weather permitting. One south bound main lane will remain open. TxDOT, 737.600.3137
ED J.L. GREEN: Advance notice of street maintenance from Sessom Dr. to Laurel Ridge on March 8 through April 11 from 8 a.m. to 5 p.m daily, except weekends. Please park your vehicle off the street or it may be towed. Project is estimated to last approximately 4 to 6 weeks, weather permitting. City of San Marcos Street Dept., 512.393.8025
EAST SAN ANTONIO STREET: Every Saturday from 8 a.m. – 3 p.m.  Half a block of street closed from the alley to N. LBJ for the Farmers Market on the Square. Main Street Program, 512.393.8430
LONG TERM ROAD PROJECTS:
CENTERPOINT/TANGER PREMIUM OUTLET INTERSECTION:  The intersection will be under construction for a new traffic signalization project and is scheduled for completion Spring 2016. There will be alternating lane closures at the mall entrances during the day. Pedestrian movement may be altered due to ramp and sidewalk modifications. City of San Marcos Traffic Dept., 512.393.8034
HOLLAND/MOORE ST: Moore Street at Holland will be closed until May 23 to correct traffic flow issues and to make enhancements to the Holland Street entrance into the Speck garage; however, the east entrance into Speck Garage on Academy St. will remain open.
NORTH LBJ FROM CAMARO WAY TO CRADDOCK: This road will be open to two-way traffic, but the lanes will be shifted west to allow space for the City contractor to construct a new lift station on the corner of N. LBJ and Craddock. Project will last until summer 2016. Engineering/Capital Improvements, 512.393.8130
817 CHESTNUT ST: One lane will be closed for new construction to site through June 2. Street will continue to be passable to all traffic. J4 Development, 469.236.0922
MOORE STREET: Moore Street is closed from Read to Holland Street until early 2016 for dormitory construction. Texas State University FPDC, 512.245.2202 
Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.