Short & Long Term Road Construction Projects Affecting San Marcos Traffic Saturday, March 3 – Friday, March 9, 2018
LOCATION | BEGIN DATE | EST. END DATE |
---|---|---|
LP 82: Both East and West Bound Lanes will be reduced to a single lane during daytime hours. TXDOT, 512.393.8130. | Mar. 12 9 AM |
Mar. 16 3PM |
DURANGO STREET: Durango St. between Jaurez St and Luciano Flores Street will be closed for reclaimed waterline project. Rockin Q Construction, 512.738.6666. | Oct. 30 8 AM |
April 30 5 PM |
LP 82: LP 82 from Charles Austin to Mill Street will be closed in both directions on Feb. 25-26 from 6 p.m. – 6 a.m. TxDOT, 512.393.8130. | Mar. 11 6 PM |
Mar. 11 6 AM |
COERS CIRCLE: Coers Circle will be closed in both directions for gas line trenching. Cliff Wharton, 830.643.6927. |
March 14 8 AM |
March 16 5 PM |
COERS DRIVE: Coers Drive will be reduced to one lane March 12-23 from 8 a.m. – 5 p.m. for gas line trenching. Cliff Wharton, 830.643.6927. | March 12 8 AM |
March 23 5 PM |
LONG TERM CLOSURE – SAN MARCOS PARKWAY: San Marcos Parkway to Leah Ave. will have a Street Overlay Project March 7-30, 2018 from 8 a.m. to 5 p.m. The street will be open to traffic, but use caution, drive slowly. Watch for heavy equipment, construction workers and traffic control flaggers. We ask that all vehicles be parked off street or they may be towed at owners; expense. Jesse Shroyer 512.393.8036. | Mar. 7 8 AM |
Mar. 30 5 PM |
LONG TERM CLOSURE – OAK RIDGE DRIVE: Single lane closures daily for the installation of utility mains City of San Marcos Engineering/CIP Dept., 512.393.8130. | Present | Summer 2018 |
LONG TERM CLOSURE – WOODS STREET: A segment of Woods Street between Comanche and North Street will be closed during construction of the new Texas State University Engineering & Science Building until Aug. 2018. Project Manager Scott Rouse, 512.245.2202. | Aug. 2015 |
Aug. 2018 |
LONG TERM CLOSURE – MCKIE ST: Mckie St. will be closed from the 400 Block to the 600 Block in both directions for the installation of new water main. Erik Pelayo, Under Ground Water Solutions Co., 512.278.9333. | Dec. 1 7 AM |
Mar. 30 6 PM |
LONG TERM CLOSURE – MCKIE ST: Mckie St. will be closed from IH-35 Frontage Rd. to apartment entrance for utility installation. Rockin Q Construction, 512.738.6666. | Feb. 2018 8 AM |
Dec. 7 5 PM |
LONG TERM CLOSURE – VISTA ST: All lanes in both directions will be closed from 310 – 312 Vista Street for utility construction. Texas State University, 512.245.2202. | Present | Aug. 1 2018 |
LONG TERM CLOSURE – SESSOM DR: Various lane closures from N. LBJ to Aquarena Springs Dr. for road construction. City of San Marcos Engineering/CIP Dept, 512.393.8130. | Present | March 2018 |
LONG TERM CLOSURE – LP 82/AQUARENA SPRINGS: TxDOT introduced a new traffic signal at the intersection of Post/Bobcat traffic will be detoured to the new signal. TxDOT, 512.393.8130. | February 2017 |
Spring 2018 |
LONG TERM CLOSURE – EAST SAN ANTONIO STREET – EVERY SATURDAY: Half a block closed from the alley to N. LBJ every Saturday from for the Farmers Market on the Square. Main Street Program, 512.393.8430. | Saturday 8 AM |
Saturday 3 PM |
The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…
The San Marcos River Rollers have skated through obstacles after taking a two-year break during…
San Marcos Corridor News has been reporting on the incredible communities in the Hays County…
Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…
Looking to adopt or foster animals from the local shelter? Here are the San Marcos…
The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…
This website uses cookies.