What To Expect On San Marcos Roads During Week Of Sunday, Dec 17 – Saturday, Dec. 23

San Marcos’ Weekly Road Construction & Traffic Report

Short & Long Term Road Construction Projects Affecting San Marcos Traffic Sunday, December 17  – Saturday, December 23, 2017

Can’t see the whole table? Touch it and scroll right.

WEEKLY ROAD CONSTRUCTION SCHEDULE 

LOCATION BEGIN DATE EST. END DATE
LP 82/BRIDGE RAIL: TxDOT will reduce traffic to a single lane Dec.18 – 21, 2017 from 9 a.m. to 3:30 p.m. for both east-and westbound lanes to work on the bridge. Lorri Pavliska, 512.284.1683.   Dec. 18    9 AM     Dec. 21     3:30 PM 
CHESTNUT STREET: From Walnut to Acorn will be closed daily for sidewalk construction. City of San Marcos Engineering/CIP Dept., 512.393.8130.    Dec. 11      Jan. 31   
DURANGO STREET: Durango St. between Jaurez St and Luciano Flores Street will be closed for reclaimed waterline project. Rockin Q Construction   512.738.6666    Oct. 30    7 AM     Dec. 24    5 PM
POST ROAD: The Blanco River Bridge was closed on July 24 for new bridge construction. Traffic needs to detour to alternative routes. Hays County. July 24 NOT LISTED
LP 82: TxDOT will close Charles Austin to Mill St. on Dec. 19, 2017, from 8 p.m. to Dec. 20, 2017, at 6 a.m. to complete a bridge pour for deck spans 1 & 2. Lorri Pavliska, 512.284.1683.     Dec. 19     8 PM     Dec. 20     6 AM
CM ALLEN PKWY: The 100 block of CM Allen Pkwy will be reduced to one lane Dec. 21 – 25, 2017 from 8 a.m. to 5 p.m. for overhead utility work. Haley Norman, 512.945.0018.  Dec. 21   8 AM    Dec. 25    5 PM
LONG TERM CLOSURE – MCKIE ST: Mckie St. will be closed from IH35 frontage Rd. to apartment entrance for utility installation. Rockin Q Construction, 512.738.6666.    July 24     7 AM     Dec. 1       5 PM
LONG TERM CLOSURE – VISTA ST: All lanes in both directions will be closed from 310 – 312 Vista Street for utility construction Texas State University, 512.245.2202. Present    July 31    2018
LONG TERM CLOSURE – SESSOM DR: Various lane closures from N. LBJ to Aquarena Springs Dr. for road construction. City of San Marcos Engineering/CIP Dept, 512.393.8130. Present Jan. 2018
LONG TERM CLOSURE – WOODS ST: A segment of Woods St between Comanche and North Street will be closed during construction of the new Texas State University Engineering & Science Building. Project Manager Scott Rouse, 512.245.2202. August 2015 August  2018
LONG TERM CLOSURE – LP 82/AQUARENA SPRINGS: TxDOT introduced a new traffic signal at the intersection of Post/Bobcat traffic will be detoured to the new signal. TxDOT, 512.393.8130.     Feb.     2017 Spring 2018
LONG TERM CLOSURE – EAST SAN ANTONIO STREET – EVERY SATURDAY: Half a block closed from the alley to N. LBJ every Saturday from 8 a.m. – 3 p.m. for the Farmers Market on the Square. Main Street Program, 512.393.8430.  N/A N/A 


 

Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.