Short & Long Term Road Construction Projects Affecting San Marcos Traffic Sunday, July 22, 2018

Please use caution, drive slowly and watch for heavy equipment,
construction workers, and traffic control flaggers.

Can’t see the whole table? Touch it and scroll right.

WEEKLY ROAD CONSTRUCTION SCHEDULE

LOCATION BEGIN DATE EST. END DATE
LP 82: Both the East-and Westbound lanes will be reduced to a single lane during night time hours. TxDOT, 512.393.8130
July 22
8:00 AM
July 26
6 PM
HOPKINS STREET: Hopkins St. between Johnson Street and Travis Street will be closed with a complete closure of Mitchell Avenue from Hopkins Street to San Antonio Street for the duration of the project. SMEU, David Gaona, 512.393.8322 June 11
7 AM
Completion
Date
TBD
MEDICAL PARKWAY: Medical Parkway from Wonder World to Leah Ave. is scheduled to undergo a Slurry Seal Project. Please use caution, drive slowly and watch for heavy equipment, construction workers, and traffic control flaggers. All vehicles should be parked off the street. Or they may be towed at owner’s expense. Jesse Shroyer, 512.393.8036 June 27
7 AM
July 31
5:30 PM
CM ALLEN: CM Allen at Mariposa Street will be closed for Utility Installation. Rockin Q Construction, Bob Quinn, 512.738.6666 July 16
8 AM
Completion Date TBD
6 PM
THORPE LANE: Thorpe Lane from Hopkins St. to Aquarena Springs is scheduled to undergo a base failure and asphalt repair project. Please use caution, drive slowly and watch for heavy equipment, construction workers, and traffic control flaggers. All vehicles should be parked off the street. Or they may be towed at owner’s expense. Jesse Shroyer, 512.393.8036
July 23
7 AM
July 27
5:30 PM
1100 BLOCK OF HOPKINS: 1100 Block of Hopkins Street between Bishop Street and Johnson Street is scheduled to undergo a base failure and asphalt repair project. Please use caution, drive slowly and watch for heavy equipment, construction workers, and traffic control flaggers. All vehicles should be parked off the street. Or they may be towed at owner’s expense. Jesse Shroyer, 512.393.8036
July 23
7 AM
July 23
4:30 PM
LONG TERM CLOSURE – STUDENT CENTER DRIVE: Student Center Drive from Matthews to the North Loading Dock of the Alkek Library will be closed for the expansion of the LBJ Student Center. Service and delivery access to Alkek Library and Derrick Hall loading docks will be available, via Russell and Pickard Streets. Texas State University, 512.245.2202
Current Jan. 21
2020
LONG TERM CLOSURE – CRADDOCK AVENUE: Craddock Avenue between Old Ranch Road 12 and Bishop Street will have partial lane closures for median work. Community Enhancement, Amy Kirwin, 512.393.8419 Current
8 AM
Sept. 30
4 PM
LONG TERM CLOSURE – CHEATHAM STREET & GUADALUPE: Cheatham Street and the 400-500 Blocks of Guadalupe will have partial lane closures for new construction. Gary Bellomy, Cheatham Street, L.P., 512.694.8839 Present
Dec. 31
2018


LONG TERM CLOSURE – OAK RIDGE DRIVE: Single lane closures daily for utility installation. City of San Marcos Engineering/CIP Dept., 512.393.8130 Present Sept.
3:30 PM
LONG TERM CLOSUREWOODS STREET: A segment of Woods Street between Comanche and North Street will be closed during construction of the new Texas State University Engineering & Science Building. Scott Rouse, Project Manager,  512.245.2202 Aug.
2015
Aug.
2018
LONG TERM CLOSURE MCKIE STREET: Mckie St. will be closed from IH-35 Frontage Rd. to apartment entrance for utility installation. Rockin Q Construction, 512.738.6666 Current
8 AM
Dec. 7
5 PM
LONG TERM CLOSURE – CONCHO STREET: Eastbound Concho Street between LBJ and Guadalupe will be closed, LBJ and Guadalupe will also have narrow lanes between University Drive and Concho Street, through the summer of 2020 for Construction. 3411 Builders, Inc., Richard Bagby, 832.449.0328
Aug. 6
2018


July
2020
LONG TERM CLOSURE – CM ALLEN: CM Allen between University Drive and Hopkins Street will be closed for the Reconstruction of the Roadway. City of San Marcos Engineering/CIP Dept., 512.393.8130 July 25
9 AM
Apr. 2019
5 PM
** CLOSURE EVERY SATURDAY – EAST SAN ANTONIO STREET: Half a block closed from the alley to N. LBJ every Saturday from for the Farmers Market on the Square. Main Street Program, 512.393.8430 Every
Saturday
8 AM
Every
Saturday
3 PM


 

Share
Published by
Staff

Recent Posts

San Marcos City Council reviews Sidewalk Maintenance and Gap Infill Program

The San Marcos City Council received a presentation on the Sidewalk Maintenance and Gap Infill…

2 years ago

San Marcos River Rollers skate on and rebuild

The San Marcos River Rollers have skated through obstacles after taking a two-year break during…

2 years ago

After 8 Years, San Marcos Corridor News Bids Our Readers Farewell

San Marcos Corridor News has been reporting on the incredible communities in the Hays County…

2 years ago

High bacteria levels at Jacobs Well halts swimming season

Visitors won't be able to swim in the crystal clear waters of the Jacobs Well Natural…

2 years ago

Pets of the Week: Meet Sally & Nutella!

Looking to adopt or foster animals from the local shelter? Here are the San Marcos…

2 years ago

Texas still leads in workplace deaths among Hispanics

The Lone Star State leads the nation in labor-related accidents and especially workplace deaths and…

2 years ago

This website uses cookies.