Staff Reports

SAN MARCOS – As the city of San Marcos grows, road and sidewalk construction increases. San Marcos City Council has also taken the initiative to make the area more walkable and bike-friendly for residents.

Below is a list of construction projects updated weekly throughout San Marcos that may affect your drive around the city. Residents can also find updates on when the projects will be complete and the overall construction progress.

.

Projects In Construction

.

Feltner Alley Wastewater Replacement

Feltner Alley Wastewater Replacement – 167

Water Construction N/A
Wastewater Construction N/A
Stormwater Construction 30%
Roadway Construction N/A
% Contract Billed 10%
Construction Completion March 2022
Project Update February 2022

.

.

Bike Lane Signal

Guadalupe St Improvements – Bike Lane Signal – 477

Water Construction N/A
Wastewater Construction N/A
Stormwater Construction N/A
Roadway Construction 95%
% Contract Billed 90%
Construction Completion Winter 2022
Project Update February 2022
   

.

.

Guadalupe St Imp – Sidewalk and Landscaping

Guadalupe St Imp – Sidewalk and Landscaping – 477

Water Construction N/A
Wastewater Construction N/A
Stormwater Construction N/A
Roadway Construction 75%
% Contract Billed 70%
Construction Completion Winter 2022
Project Update February 2022

.

.

Hopkins Street Improvements – Bishop to Moore

Hopkins Street Improvements – Bishop to Moore – 90

Water Construction 95%
Wastewater Construction 75%
Stormwater Construction 95%
Roadway Construction 75%
% Contract Billed 77%
Construction Completion Summer 2022
Project Update February 2022

.

.

                      

Mobility IH35 – IH35 at Hwy 123

 

Water Construction 30%
Wastewater Construction 30%
Stormwater Construction Check TxDOT Webpage
Roadway Construction Check TxDOT Webpage
% Contract Billed N/A
Construction Completion Winter 2025
Project Update February 2022

.

.

Mobility IH35 – River Ridge Pkwy to Loop 82

Mobility IH35 – River Ridge Pkwy to Loop 82 – 629

Water Construction 10%
Wastewater Construction N/A
Stormwater Construction Check TxDOT Webpage
Roadway Construction Check TxDOT Webpage
% Contract Billed N/A
Construction Completion Summer 2022
Project Update January 2022

.

.

Rio Vista Falls Maintenance

Rio Vista Falls Maintenance – 743  

Water Construction N/A
Wastewater Construction N/A
Stormwater Construction 30%
% Contract Billed 10%
Construction Completion March 2022
Project Update February 2022

                                                               

.

.

Sessom Creek Improvements Phase I

Sessom Creek Improvements Phase I – 521

Water Construction 0%
Wastewater Construction 50%
Stormwater Construction 0%
Roadway Construction N/A
% Contract Billed 14%
Construction Completion Fall 2023
Project Update February 2022

.

.

Uhland Road Improvements – CDBG-DR

  

Uhland Road Improvements – CDBG-DR

Water Construction 35%
Wastewater Construction 0%
Stormwater Construction 30%
Roadway Construction 28%
% Contract Billed 29%
Construction Completion Winter 2023
Project Update February 2022

.