183 South Scheduled Road Construction, Closures, Detours For Week Of Jan. 4

Staff Report

Austin — Short and long term lane, road closures, and detours that may impact drivers along US 183 and adjacent roadways in east Austin.

Below is an overview of the 183 South project’s lane, road, and ramp closures. Work continues along US 183, including bridge construction, roadway installation, sound wall work, utility work.

The Central Texas Regional Mobility Authority is an independent government agency created in 2002 to improve the transportation system in Williamson and Travis counties.

The Mobility Authority is overseen by a seven-member Board of Directors. The Governor appoints the Chairman, and the Travis and Williamson counties Commissioners Courts each appoint three members to serve on the Board.

• US 183 Special Closure & Detour •

SOUTHBOUND US 183 REDUCED TO ONE LANE
BETWEEN MANOR ROAD AND LOYOLA LANE

Tolls Temporarily Waived on 183 Toll Road at
MLK Blvd/FM 969 Exit

PLEASE NOTE THAT ALL CLOSURES ARE WEATHER PERMITTING AND SUBJECT TO CHANGE

Austin, Texas — Beginning as early as the evening of Sunday, November 22, 2020*, and lasting approximately five months, the southbound US 183 non-tolled general-purpose lanes between Manor Road and Loyola Lane will be reduced to one lane. The closure is necessary to make concrete pavement repairs in the area.

To minimize the inconvenience to drivers during the closure, the Central Texas Regional Mobility Authority will be temporarily allowing southbound US 183 drivers to enter the 183 Toll Road at Manor Road and to use the MLK Blvd/FM 969 exit without paying a toll.

Normal tolls will be charged to drivers who continue south on the 183 Toll Road past the exit signed for MLK Blvd/FM 969.

*Dates are subject to change based on weather and other circumstances.

 


.

US 183 Short & Long Term Closures & Detours

..

Short Term

LANE CLOSURE — 12/29/20 to 01/06/21 — PEDESTRIAN BRIDGE CONSTRUCTION
Tuesday (12/29) and Sunday-Tuesday (1/3-5) 8 p.m. to 6 a.m., US 183 southbound mainlanes at Hudson St. and the on-ramp at Smith Rd. will be closed. Detour via US 183 general-purpose to on-ramp at Interchange Blvd.

RAMP CLOSURE — 01/03/21 to 01/10/21 — ROADWAY BASE INSTALLATION
Sunday (1/3/21) 6 p.m. through Sunday (1/10/21) 6 a.m., US 183 northbound to SH 71 westbound cloverleaf will be closed. Detour via SH 71 eastbound to Spirit of Texas Dr. U-turn.

LANE CLOSURE — 01/03/21 to 01/05/21 — ROADWAY BASE INSTALLATION
Sunday (1/3) 6 p.m. to 6 a.m., US 183 north-to-south U-turn at MLK Blvd will be closed. Detour through signalized intersection at MLK Blvd. Monday (1/4) 8 p.m. to 6 a.m., US 183 north-to-south U-turn at MLK Blvd will be closed. Detour through signalized intersection at MLK Blvd.

LANE CLOSURE — 01/03/21 to 01/06/21 — DRAINAGE WORK
Sunday-Tuesday (1/3-1/5) 8 p.m. to 6 a.m., US 183 northbound bypass closed at MLK Blvd. Detour through signalized intersection at MLK Blvd.

RAMP CLOSURE — 01/03/21 to 01/06/21 — DRAINAGE WORK
Sunday-Tuesday (1/3-1/5) 8 p.m. to 6 a.m., northbound 183 Toll exit to MLK/FM 969 will be closed. Detour to Last Free Exit towards Techni Center.

LANE CLOSURE — 01/04/21 to 01/05/21 — GUARDRAIL WORK
Monday–Tuesday (1/4-1/5) 9 a.m. to 3 p.m., US 183 northbound bypass right lane closed at MLK Blvd. US 183 northbound left general-purpose lane closed between Marcel Gres and 51st Street.

LANE CLOSURE — 01/04/21 to 01/08/21 — DRAINAGE WORK
Monday-Thursday (1/4-1/7) 8 p.m. to 6 a.m., US 183 northbound right lane will be closed from Techni Center Dr. to MLK Jr. Blvd.

LANE CLOSURE — 01/05/21 to 01/05/21 — GUARDRAIL WORK
Tuesday (1/5) 9 a.m. to 3 p.m., US 183 southbound left mainlane will be closed between Vargas Road and SH 71.

LANE CLOSURE — 01/05/21 to 01/05/21 — DRAINAGE WORK
Tuesday (1/5) 9 a.m. to 3 p.m., northbound 183 Toll left lane will be closed between 51st St. and Loyola Ln.

LANE CLOSURE — 01/05/21 to 01/06/21 — PAVING
Tuesday (1/5) 8 p.m. to 6 a.m., US 183 northbound exit ramp at Thompson closed. Montopolis traffic detour via Airport Blvd., U-turn Levander to southbound Airport ramp. US 183 northbound general-purpose at Thompson closed. Detour via Thompson to Hergotz to US 183.

LANE CLOSURE — 01/06/21 to 01/09/21 — DRAINAGE WORK
Wednesday–Friday (1/6-1/8) 8 p.m. to 6 a.m., US 183 northbound left general-purpose lane between Harold Court and Techni Center Drive and 183 Toll entry ramp at Central Avenue will be closed. Detour via MLK bypass and entry ramp under MLK Blvd.

LANE CLOSURE — 01/06/21 to 01/07/21 — GUARDRAIL WORK
Wednesday (1/6) 8 p.m. to 6 a.m., US 183 southbound mainlanes closed at Hudson Street. US 183 southbound left general-purpose lane closed between Vargas and Patton. All traffic use southbound general-purpose lanes.

LANE CLOSURE — 01/06/21 to 01/09/21 — DRAINAGE WORK
Wednesday-Friday (1/6-1/8) 8 p.m. to 6 a.m., US 183 northbound right general-purpose lane will be closed between Harold Court and MLK Jr. Blvd.

RAMP CLOSURE — 01/06/21 to 01/09/21 — DRAINAGE WORK
Wednesday-Friday (1/6-1/8) 8 p.m. to 6 a.m., northbound 183 Toll entry ramp at Central Ave. will be closed. Detour to entry ramp at MLK bypass.

LANE CLOSURE — 01/07/21 to 01/09/21 — DRAINAGE WORK
Wednesday-Friday (1/6-1/8) 8 p.m. to 6 a.m., US 183 southbound right general-purpose lane will be closed between MLK Jr. Blvd. and Bluestein Dr.

RAMP CLOSURE — 01/07/21 to 01/08/21 — GUARDRAIL WORK
Thursday (1/7) 8 p.m. to 6 a.m., SH 71 westbound direct connector to US 183 northbound closed. Detour via Old Bastrop Highway.

RAMP CLOSURE — 01/07/21 to 01/09/21 — DRAINAGE WORK
Thursday-Friday (1/7-1/8) 8 p.m. to 6 a.m., southbound 183 Toll exit ramp at Hudson Street will be closed. Detour at 51st Street/MLK Jr. Blvd. exit ramp.

ROAD CLOSURE — 01/08/21 to 01/09/21 — DRAINAGE WORK
Friday (1/8) 8 p.m. to 10 a.m., US 183 southbound entry ramps to Loyola Lane and southbound general-purpose lanes between Springdale/Manor Rd. and Loyola Lane closed. Detour to MLK exit and utilize the U-turn to access Loyola Lane.

LANE CLOSURE — 01/08/21 to 01/10/21 — PAVING
Friday (1/8) 8 p.m. to Sunday (1/10) 3 p.m., US 183 southbound general-purpose left lane closed between Loyola Lane and 51st Street.

 


.

Long Term

RAMP CLOSURE — 05/10/20 to 01/10/21 — ROADWAY BASE INSTALLATION
Beginning as early as this Sunday, May 10, the exit to E. Riverside Drive from westbound SH 71 will be closed for several months. Detour to East Riverside Dr. via Montopolis Dr. and to reach SB US 183 use Patton Avenue U-turn..