Top 21 Road Construction Projects, Closures To Avoid In San Marcos This Week

The long & short term road construction projects that could affect your drive… Please use caution, drive slowly and watch for heavy equipment, construction workers, and traffic control flaggers.

 

Can’t see the entire table below?
Touch it and scroll right.

z

WEEKLY ROAD CONSTRUCTION SCHEDULE

LOCATION BEGIN DATE EST. END DATE
KISSING ALLEY: Kissing Alley will be closed for a Community Service Project. Josie Falletta, 512.393.8430
Apr. 5
7 AM
Apr. 5
10 PM

THORPE LANE: The 1300 BLK of Thorpe Lane will be closed for construction. KBR Builders Inc. No contact phone available.
Mar. 29
7 AM
Apr. 5
6 PM
ROOSEVELT STREET: Roosevelt Street from Eisenhower Street/Patton Street will have partial lane closures with flagger control for wastewater line construction – Cox Commercial Construction 956.601.1645 Mar. 1
7 AM
Apr. 30
5 PM
ALABAMA STREET: 500-800 Block of Alabama Street will have lane closure with flagger control for Wastewater line construction. Cox Commercial Construction, 956.601.1645 Mar. 1
5 PM
Apr. 30
5 PM
AQUARENA SPRINGS: Westbound Aquarena Springs at Charles Austin will be reduced to one lane for a water service line repair. City of San Marcos Water Department, 512.393.8010 Apr. 7
8 AM
Apr. 8
5 PM
SESSOM DRIVE: Sessom Drive from Alamo Street to Comanche Street will have a partial lane closure for a new sidewalk installation – Public Services – 512.393.8036
Apr. 1
8 AM
Apr. 15
5 PM
LONG TERM — BROWN STREET: Brown Street between Prospect Street and Belvin Street will be closed for utility installation. Jacob Snyder, 214.298.4578 Apr. 3
7 AM
May 20
5 PM
LONG TERM — HUTCHINSON STREET: Hutchinson Street between Guadalupe Street and Telephone Alley will be closed for utility Installation. Don Alcala, 512.393.8307 Mar. 29
8 AM
Apr. 5
5 PM
LONG TERM — CAMACHO STREET/MACARTHUR STREET: 200 – 300 Block of Camacho Street/MacArthur Street will have lane closure with flagger control for Wastewater line construction. Cox Commercial Construction, 956.601.1645 Mar. 18
7 AM
Apr. 30
5 PM
LONG TERM — RAILROAD STREET: Railroad Street between Eisenhower and Gomez Street will be closed for utility installation. Cox Commercial Construction, 956.601.1645 Mar. 1
7 AM
Apr. 30
5 PM
LONG TERM CLOSURE — MILL STREET: Mill Street between 500 and 700 blocks will have partial lane closure for the reconstruction of waterline services and potholing. City of San Marcos Engineering/CIP Dept. 512.393.8130, Smith Contracting, 512.789.5441 Dec
2018
Fall of
2019
LONG TERM — NORTH BISHOP STREET: Westbound Bishop Street between Belvin Street and Prospect Street will be closed for new sidewalk installation. Winters Construction, Charlie Winters, 210.224.7920
Oct. 1
7 AM
Apr. 30
6 PM
LONG TERM — CHEATHAM STREET: Cheatham Street and the 400-500 Blocks of Guadalupe will have partial lane closures for new construction. Gary Bellomy, Cheatham Street, L.P. 512.694.8839
Current
July 2019
LONG TERM CLOSURE — HOPKINS STREET: A portion of Hopkins St. will be closed for a road widening project and underground utility installation. Richard Reynosa, 512.393.8235
Nov. 2018
Fall 2020
LONG TERM CLOSURE – STUDENT CENTER DRIVE: Student Center Drive from Matthews to the North Loading Dock of the Alkek Library will be closed for the expansion of the LBJ Student Center. Service and delivery access to Alkek Library and Derrick Hall loading docks will be available, via Russell and Pickard Streets. Texas State University, 512.245.2202
Current Jan. 2020
LONG TERM CLOSURECOERS STREET: Coers Street between Old RR 12 to Owens Street will have southbound lane closure to through traffic for drainage improvement. Denbow Company, 512.264.2767 Oct. 1
7 AM
Apr. 30
5:30 PM
LONG TERM CLOSURE – CONCHO STREET: Eastbound Concho Street between LBJ and Guadalupe will be closed, LBJ and Guadalupe will also have narrow lanes between University Drive and Concho Street for Construction. 3411 Builders, Inc., Richard Bagby, 832.449.0328
Aug.
2018


July
2020
LONG TERM – SESSOM DRIVE: Sessom Drive from Aquarena Springs to ED J L Green will be closed for waterline installation. PROTA Construction, Kermith Garcia, 512.535.2555
Dec. 17
7 AM
Apr. 5
3 PM
LONG TERM – TRAVIS STREET DRAINAGE PROJECT: Traffic impacts include the intersection of MLK at Armstead, Armstead from MLK to San Antonio Street, San Antonio Street from Travis Street to Armstead and Travis Street from San Antonio St. to Hopkins Street will be closed for utility installation. Commercial Construction, Darren Okruhlik, 956.601.1645

Traffic will have intermittent lane closure for video detection, camera replacement, and roadway striping at the following locations starting
April 1-5, 2019:
1.
Cheatham at LBJ
2. Aquarena at Sessom
3. Sadler at Wonder World
4. Aquarena at Thorpe
5. Craddock at Wonder World
6. Old RR 12 from Craddock to Hopkins
7. Aquarena Springs from IH 35 to River

Mar. 1
7 AM
Nov. 2019
5 PM
LONG TERM CLOSURE – CM ALLEN PARKWAY: CM Allen between University Drive and Hopkins Street will be closed for the reconstruction of roadway. COSM Engineering/CIP Dept., 512.393.8130 July 25
9 AM
Apr. 2019
5 PM
**CLOSURE EVERY SATURDAY – EAST SAN ANTONIO STREET: Half a block closed from the alley to N. LBJ every Saturday from for the Farmers Market on the Square. Main Street Program, 512.393.8430 Every
Saturday
8 AM
Every
Saturday
3 PM

 