I-35 Corridor Closures & Detours You Need To Know Before You Start Your Weekly Commute

.
TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.

Remember to support your local businesses as they are still open during construction…

I-35 CAPITAL AREA CORRIDOR MOBILITY
…..Closures, Detours, Traffic Alerts for August 22 – August 28, 2020

 


I-35 AT POSEY ROAD

PROJECT OVERVIEW | This project will construct a new overpass on I-35 over Posey Road, add two new U-turns in each direction at Posey Road, perform ramp reversals and convert two-way frontage roads to one-way.

Currently, the I-35 main lanes go under Posey Road with the new configuration, I-35 main lanes will going over Posey Road.

This project is made possible by a partnership between Hays County/TxDOT and is expected to cost $31.7 million funded by TxDOT.

The I-35 and Posey Road construction started in February 2019 and anticipated construction completion is planned for mid-2021. The project contractor is Webber, LLC.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Posey Road bridge closed at I-35.
    ° Until further notice
  • Northbound I-35 Posey Road exit (#199) and Centerpoint Road exit (#200) are closed.
    ° Until further notice
  • Southbound I-35 Posey Road exit (#199) and York Creek Road exit (#196) are closed.
    ° Until further notice
  • Southbound I-35 reduced to one lane nightly from Centerpoint Road to York Creek Road.
    ° Friday, Aug. 21 through Saturday, Aug. 22 from 9 PM until 5 AM
  • Northbound and southbound I-35 right lane closed nightly from York Creek Road to Centerpoint Road. Multiple ramps will also be closed.
    ° Saturday, Aug. 22 through Sunday, Aug. 23 from 9 PM until 5 AM

Read more on construction phasing and additional project details HERE.

I-35 FROM STASSNEY LANE TO WILLIAM CANNON DRIVE

PROJECT OVERVIEW | The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek. Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 main lanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.

This major project is estimated to cost $78.8 million. Construction started in July 2016 with the anticipated completion in late 2020. The contractor for this project is OHL, USA, Inc.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 reduced to one lane from Slaughter Lane to William Cannon Drive. The William Cannon Drive entrance ramp will also be closed.
    ° Friday, Aug. 21 from 9 PM until 8 AM
  • Southbound I-35 frontage road left lane closed from William Cannon Drive to Chaparral Road.
    ° Friday, Aug. 21 from 9 PM until 5 AM
  • Northbound I-35 right lane closed nightly from Slaughter Lane to Teri Road.
    ° Friday, Aug. 21 through Sunday, Aug. 23 from 9 PM until 5 AM
  • Southbound I-35 frontage road right lane closed at Stassney Lane.
    ° Saturday, Aug. 22 from 9 AM until 3 PM
  • Southbound I-35 frontage road left lane closed at Slaughter Lane.
    ° Saturday, Aug. 22 from 9 AM until 3 PM
  • Southbound I-35 frontage road left lane closed from William Cannon Drive to Foremost Drive.
    ° Saturday, Aug. 22 from 9 AM until 3 PM
  • Northbound and southbound I-35 frontage road reduced to one lane from William Cannon Drive to Stassney. Lane
    ° Saturday, Aug. 22 from 9 AM until 3 PM
  • Eastbound Stassney Lane right lane closed at the I-35 frontage road.
    ° Saturday, Aug. 22 from 9 AM until 3 PM
  • Eastbound William Cannon Drive reduced to one lane at the I-35 frontage road.
    ° Saturday, Aug. 22 from 9 AM until 3 PM
  • Northbound I-35 right lane closed from William Cannon Drive to Stassney Lane. The William Cannon Drive entrance ramp will also be closed.
    ° Monday, Aug. 24 through Tuesday, Aug. 25 from 9 PM until 5 AM
  • Northbound and southbound I-35 right lane closed from Slaughter Lane to SH 71.
    ° Monday, Aug. 24 through Thursday, Aug. 27 from 9 PM until 5 AM
  • Westbound William Cannon Drive right lane closed daily at the I-35 frontage road.
    ° Monday, Aug. 24 through Saturday, Aug. 29 from 9 AM until 3 PM

Read more on construction phasing and additional project details HERE.

I-35 AT NORTHWEST BOULEVARD

PROJECT OVERVIEW | This project will reconstruct the Northwest Boulevard bridge over I-35. The project will also construct a four-lane roadway with a roundabout and intersection improvements that connect to the new bridge.

The construction started in September 2019 and is anticipated to conclude in Fall 2020, weather permitting. The projected project cost is estimated at $8.15 million and the contractor is Chasco Constructors.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

…………Closures are weather permitting

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 FROM RUNDBERG LN. TO US 290 EAST

PROJECT OVERVIEW | This project includes main lanes and frontage road reconstruction and the addition of three new flyovers at US 183.

I-35 from Rundberg Lane to US 290 East is estimated to cost $124.2 million and is made possible by Texas Clear Lanes Congestion Relief Fund.

The construction commenced in January 2018 with an anticipated completion date in mid-2021. The contractor for this project is J.D. Abrams.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Southbound US 183 Cameron Road exit closed.
    ° Through September
  • Northbound US 183 frontage road reduced to one lane from I-35 to Gessner Drive.
    ° Through September
  • Southbound US 183 frontage road closed from I-35 to Providence Avenue.
    ° Sunday, Aug. 23 from 8 PM until 5 AM
  • Southbound I-35 frontage road reduced to one lane nightly from Wonsley Drive to US 183.
    ° Sunday, Aug. 23 through Thursday, Aug. 27 from 9 PM until 5 AM
  • Southbound I-35 right two lanes closed nightly from Powell Lane to US 183. The Rundberg entrance ramp will also be closed.
    ° Sunday, Aug. 23 through Thursday, Aug. 27 from 9 PM until 5 AM
  • Northbound and southbound I-35 frontage road reduced to one lane nightly from Blackson Avenue to Huntland Drive.
    ° Sunday, Aug. 23 through Thursday, Aug. 27 from 9 PM. until 5 AM
  • Northbound US 183 frontage road reduced to one lane nightly from Rutherford Lane to Cameron Road.
    ° Sunday, Aug. 23 through Wednesday, Aug. 26 from 9 PM until 5 AM
  • Northbound and southbound I-35 frontage road reduced to one lane daily from Huntland Drive to US 183.
    ° Monday, Aug. 24 through Friday, Aug. 28 from 9 AM. until 3 PM
  • Southbound US 183 frontage road closed nightly from I-35 to Providence Avenue.
    ° Monday, Aug. 24 through Thursday, Aug. 27 from 9 PM until 5 AM

Read more on construction phasing and additional project details HERE.

I-35 FROM 1431 TO FM 3406 (NORTHBOUND)

PROJECT OVERVIEW | Improvements include relocating the exit ramp on the northbound I-35 frontage road to reduce vehicle congestion on I-35 mainlanes and improve the northbound frontage road by adding an extended exit lane between RM 1431 and FM 3406.

The estimated construction cost is $10.7 million. Construction commenced in mid-2019 with an anticipated completion date for early 2021. Jordan Foster Construction is the contractor for this project.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 frontage road reduced to one lane from Jeffrey Way to the RM 1431 exit (#256).
    ° Through early 2021

Read more on construction phasing and additional project details HERE.

I-35 FROM GRAND AVENUE PARKWAY TO SH 45 NORTH

PROJECT ACTIVITY | Improvements include reversing ramps, constructing an extended entrance/exit lane on the northbound I-35 mainlanes under SH 45 North, along the frontage road, installing high-mast lighting, and improvements at Picadilly Drive and the I-35 frontage road.

The projected cost is estimated at $8.2 million and funded by CAMPO and TxDOT. Construction will start August 2020 and anticipated to be complete in mid-2021. The project contractor is Jordan Foster Construction.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 frontage road reduced to one lane nightly from Grand Avenue Parkway to SH 45 North.
    ° Sunday, Aug. 23 through Tuesday, Aug. 25 from 7 PM until 6 AM
  • Northbound I-35 frontage road closed nightly at Picadilly Drive.
    ° Sunday, Aug. 23 through Tuesday, Aug. 25 from 12 AM until 3 AM

Read more on construction phasing and additional project details HERE.

I-35 AT PARMER LANE

PROJECT OVERVIEW | Reduced congestion, improved mobility at Parmer Lane and Lamar Boulevard, operational efficiency, more reliable travel times, lower fuel consumption.

The estimated construction cost for this project is funded by Texas Clear Lanes and Capital Area Metropolitan Planning Organization (CAMPO) with an estimated cost of $24.6 million.

Construction started in July 2019 with an estimated timeline to be completed by mid-2021. Primoris Services Corporation as the project contractor.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 CORRIDOR ROAD & HIGHWAY MAINTENANCE

PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 RM 620 exit (#252B) closed nightly.
    ° Monday, Aug. 24 through Tuesday, Aug. 25 from 9 PM until 5 AM
  • Southbound I-35 frontage road right lane closed from Concordia Avenue to Luther Lane.
    ° Through December
  • Northbound I-35 reduced to one lane nightly from River Ridge Parkway to Yarrington Road. Multiple ramps will also be closed.
    ° Sunday, Aug. 23 through Monday, Aug. 24 from 8:30 PM until 5 AM
  • Northbound I-35 reduced to one lane from SH 80 to Loop 82. Multiple ramps will also be closed.
    ° Tuesday, Aug. 25 from 8:30 PM until 5 AM
  • Northbound I-35 reduced to one lane from Kyle Crossing to FM 2001.
    ° Wednesday, Aug. 26 through Thursday, Aug. 27 from 8:30 PM until 5 AM

Read more on construction phasing and additional project details HERE.