SAN MARCOS – As the city of San Marcos grows, road, drainage, and wastewater construction and improvements increase across the city. San Marcos City Council has also taken the initiative to make the area more walkable and bike-friendly for residents.
Below is a list of construction projects updated weekly throughout San Marcos that may affect your drive around the city. Residents can also find updates on when the projects will be complete and the overall construction progress.
.
• Projects In Construction •
.
Blanco Gardens Drainage Improvements – CDBG-DR

| Water Construction |
0% |
| Wastewater Construction |
0% |
| Stormwater Construction |
0% |
| Roadway Construction |
0% |
| % Contract Billed |
0% |
| Construction Completion |
June 2024 |
| Project Update |
April 2022 |
.
Feltner Alley Wastewater Replacement – 167

| Water Construction |
N/A |
| Wastewater Construction |
60% |
| Stormwater Construction |
N/A |
| Roadway Construction |
N/A |
| % Contract Billed |
40% |
| Construction Completion |
March 2022 |
| Project Update |
April 2022 |
.
Guadalupe St Improvements Bike Lane Signal – 477

| Water Construction |
N/A |
| Wastewater Construction |
N/A |
| Stormwater Construction |
N/A |
| Roadway Construction |
95% |
| % Contract Billed |
90% |
| Construction Completion |
Winter 2022 |
| Project Update |
March 2022 |
| |
.
Guadalupe St Improvements
Sidewalk and Landscaping – 477

| Water Construction |
N/A |
| Wastewater Construction |
N/A |
| Stormwater Construction |
N/A |
| Roadway Construction |
75% |
| % Contract Billed |
70% |
| Construction Completion |
Winter 2022 |
| Project Update |
March 2022 |
.
Hopkins Street Improvements – Bishop to Moore – 90

| Water Construction |
100% |
| Wastewater Construction |
80% |
| Stormwater Construction |
95% |
| Roadway Construction |
75% |
| % Contract Billed |
77% |
| Construction Completion |
Summer 2022 |
| Project Update |
March 2022 |
.
Mobility IH 35 – IH35 and Hwy 123
Improvements – 629

| Water Construction |
50% |
| Wastewater Construction |
50% |
| Stormwater Construction |
Check TxDOT Webpage |
| Roadway Construction |
Check TxDOT Webpage |
| % Contract Billed |
N/A |
| Construction Completion |
Winter 2025 |
| Project Update |
March 2022 |
.
Mobility IH35 – River Ridge Pkwy to Loop 82 – 629

| Water Construction |
90% |
| Wastewater Construction |
N/A |
| Stormwater Construction |
Check TxDOT Webpage |
| Roadway Construction |
Check TxDOT Webpage |
| % Contract Billed |
N/A |
| Construction Completion |
Summer 2022 |
| Project Update |
March 2022 |
.
Sessom Creek Improvements Phase I – 521

| Water Construction |
0% |
| Wastewater Construction |
75% |
| Stormwater Construction |
0% |
| Roadway Construction |
N/A |
| % Contract Billed |
14% |
| Construction Completion |
Fall 2023 |
| Project Update |
March 2022 |
.
Surface Water Treatment Plant Improvements – 741

|
Water Construction
|
0% |
| Wastewater Construction |
N/A |
| Stormwater Construction |
N/A |
| Roadway Construction |
N/A |
| % Contract Billed |
0% |
| Construction Completion |
September 2023 |
| Project Update |
May 2022 |
.
Uhland Road Improvements – CDBG-DR

| Water Construction |
40% |
| Wastewater Construction |
0% |
| Stormwater Construction |
45% |
| Roadway Construction |
28% |
| % Contract Billed |
35% |
| Construction Completion |
Winter 2023 |
| Project Update |
March 2022 |