What To Expect On San Marcos Roads During Week Of Aug. 20 – Aug. 26

San Marcos’ Weekly Road Construction & Traffic Report

Short & Long Term Road Construction Projects Affecting San Marcos Traffic Sunday, August 20 – Saturday, August 26, 2017

Can’t see the whole table? Touch it and scroll right.

WEEKLY ROAD CONSTRUCTION SCHEDULE 

zzz

LOCATION BEGIN DATE EST. END DATE
LOOP 82/AQUARENA SPRINGS: Loop 82/Aquarena Springs will have nighttime roadway closures from Charles Austin to Mill Street for Loop 82/Aquarena Springs bridge construction. The planned closure will happen during August 20- September 13 from 8 p.m. to 6 a.m. Monday – Thursday and from 6 p.m. to 6 a.m. Friday – Sunday. On the first two nights (Sunday 8-20 and Monday 8-21), only the eastbound right lane will be closed from Charles Austin to Mill Street. Subsequent days the closure will detour the traffic on Loop 82 at Charles Austin Drive and Mill Street. Jordan Foster Construction, 760-828-2262
Aug. 20 Mon-Thu 8 p.m. & Fri-Sun   6 p.m.    Sept. 13 Mon-Thu 8 a.m. & Fri-Sun   6 a.m. 
CHARLES AUSTIN ST: Charles Austin Street will be closed on both directions between Aquarena Springs and Hopkins for Texas State Commencement. Texas State University 512.245.7284   Aug. 19   8 a.m.  Aug. 20  6 p.m.
LONG TERM CLOSURE – VISTA ST: All lanes in both directions will be closed from 310 – 312 Vista Street for utility construction Texas State University, 512.245.2202 Present    July 31    2018
LONG TERM CLOSURE – SESSOM DR: Various lane closures from N. LBJ to Aquarena Springs Dr. for road construction. City of San Marcos Engineering/CIP Dept., 512.393.8130 Present  Jan.   2018
LONG TERM CLOSURE – N LBJ:  From Holland St. to Camaro Way, this road closure will occur during daytime construction hours. City contractor will be replacing utility lines in the area. Through traffic including Emergency Vehicles, will be routed around the project limits; please follow the detours. Engineering/Capital Improvements, 512.393.8130 Present Summer 2017
LONG TERM CLOSURE – WOODS ST: A segment of Woods St between Comanche and North Street will be closed during construction of the new Texas State University Engineering & Science Building. Project Manager Scott Rouse, 512.245.2202 August 2015 August 2018
LP 82/AQUARENA SPRINGS: TxDOT introduced a new traffic signal at the intersection of Post/Bobcat traffic will be detoured to the new signal. TxDOT, 512.393.8130     Feb.     2017 Spring 2018
LONG TERM CLOSURE – EAST SAN ANTONIO STREET – EVERY SATURDAY: Half a block closed from the alley to N. LBJ every Saturday from 8 a.m. – 3 p.m. for the Farmers Market on the Square. Main Street Program, 512.393.8430 Year  Round Year Round

 

 