MyI35 Corridor Weekly Road Construction Alerts For Saturday, Nov. 11 – Friday, Nov. 17

TxDOT, My I35 and Central Texas Regional Mobility Authority’s Weekly Corridor Traffic and Road Construction Update for the IH-35 Corridor

TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do everything they can to minimize disruptions.

•  I – 3 5   L A N E   C L O S U R E   A L E R T S  •  S A T U R D A Y  1 1 / 1 1  –  F R I D A Y  1 1 / 1 7  •



L o n g    T e r m    C l o s u r e   o f   F M   3 4 0 6   ( O l d   S e t t l e r s  B l v d )   B r i d g e 

 

PROJECT OVERVIEW | I-35 Mainlanes and FM 3406 Bridge to Close for Bridge Demolition; Long-term Detour for FM 3406 Bridge. 

The FM 3406 (Old Settlers Blvd.) bridge will be closed for widening and reconstruction for approximately 10 months.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting.

  • The FM 3406 (Old Settlers Blvd) bridge closed to eastbound traffic. Westbound traffic will detour to the newly constructed U-turn bridge. | Until Summer 2018, weather permitting

 

  • Southbound I-35 reduced to one lane under FM 3406 | Nightly from 9 p.m. until 5 a.m. Sunday, November 12 through Thursday, November 16

 

  • Westbound FM 3406 reduced to one lane between Mays St & I-35 | Nightly from 8 p.m. until 5 a.m. Sunday, November 12 through Tuesday, November 14

Read more on construction phasing and additional project details HERE.



I – 3 5   F R O M   U S   7 9   T O   S H   4 5  N O R T H

PROJECT OVERVIEWNew braided ramps (where one ramp crosses over the other) are being constructed along the northbound I-35 mainlanes between Hester’s Crossing and RM 620 to eliminate merging conflicts.

The northbound and southbound intersections of US 79 and the I-35 frontage roads are also being reconstructed to add a third left-turn for westbound US 79.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY • 

Closures are weather permitting.  

 

  • Northbound I-35 right lane closed between RM 620 & Westinghouse Rd. Ramps will close as needed. | Nightly from 9 p.m. until 5 a.m. Sunday, November 12 through Thursday, November 16

 

 

  • Northbound I-35 frontage road right lane closed between Gattis School Rd & Mays Crossing. | Daily from 9 a.m. until 4 p.m. through Tuesday, November 14

 

  • The south to northbound U-turn at I-35 & McNeil Rd closed. | Daily from 8 a.m. until 4 p.m. through Wednesday, November 15

Read more on construction phasing and additional project details HERE.



I – 3 5   A T   O L T O R F   S T R E E T

PROJECT OVERVIEW | Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads, constructing new extended entrance/exit lanes for mainlanes and ramps, and adding U-turns in both directions at Oltorf Street.

Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting.

 

 

  • Northbound I-35 frontage road right lane closed between Woodward St & Oltorf St. | Daily from 9 a.m. until 3 p.m. Monday, November 13 through Friday, November 17 

 

  • Southbound I-35 frontage road right lane closed at St. Edwards Dr. | Daily from 9 a.m. until 3 p.m. Monday, November 13 through Friday, November 17

 

  • Southbound I-35 frontage road right lane closed at Oltorf St. | Nightly from 8 p.m. until 5 a.m. Sunday, November 12 through Thursday, November 16

 

  • Various closures in both directions approaching Oltorf & across I-35. | Nightly from 8 p.m. until 5 a.m. Sunday, November 12 through Thursday, November 16

 

  • Oltorf bridge at I-35 closed. Use Woodward St or Woodland Ave. | 8 p.m. Thursday, November 16 to 5 a.m. Friday, November 17

Read more on construction phasing and additional project details HERE.



I – 3 5   F R O M   S T A S S N E Y   L A N E   T O   W I L L I A M   C A N N O N   D R.   

PROJECT  OVERVIEW| The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 mainlanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.

Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting.

 

  • Northbound I-35 flyover to westbound US 290/SH 71 closed. Detour to frontage road as alternate route. | From 7 a.m. until noon Sunday, November 12

 

  • Northbound I-35 frontage road left lane closed between Teri Ln and SH 71. | Nightly from 8 p.m. until 5 a.m. Sunday, November 12 through Thursday, November 16

 

  • Southbound I-35 entrance ramp from US 290/SH 71 will close. The southbound right lane will also close at the ramp. | From 10 p.m. until 6 a.m. Sunday, November 12

 

  • Various closures northbound I-35 frontage at William Cannon Dr. | Daily from 9 a.m. until 3 p.m. Monday, November 13 through Friday, November 17

 

  • Southbound I-35 frontage road left lane closed between Stassney Ln & William Cannon Dr exit. | Daily from 9 a.m. until 3 p.m. Monday, November 13 through Friday, November 17

 

  • Southbound I-35 frontage road right lane closed between US 290/ SH 71 & Stassney Ln. | 8 p.m. Monday, November 13 to 5 a.m. Tuesday, November 14

 

  • Southbound I-35 frontage road left lane closed between Shelby Ln & Williamson Creek. | Nightly from 8 p.m. until 5 a.m. Tuesday, November 14 through Thursday, November 16

Read more on construction phasing and additional project details HERE.



I – 3 5   F R O M   R M  1 4 3 1   T O   F M   3 4 0 6   ( S O U T H B O U N D )

PROJECT OVERVIEW | Two ramps on the southbound I-35 frontage roads between RM 1431 and FM 3406 are being reconstructed and reversed to address traffic congestion and improve I-35 frontage road and mainlane operations.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting.

 

  • Southbound I-35 entrance ramp from RM 1431 closed. Watch for workers on right shoulder in the area. | Nightly from 9 p.m. until 5 a.m. Sunday, November 12 through Tuesday, November 14   

Read more on construction phasing and additional project details HERE.



P L A N N E D  M A I N T E N A N C E

• WEEKLY CONSTRUCTION PROJECT TRAFFIC ADVISORY •

Closures are weather permitting.

 

  • Various closures on cross streets between 8th St & 38th 1/2 St | Nightly from 9 p.m. until 5 a.m. Sunday, November 12 through Thursday, November 16

 

  • Various closures northbound I-35 frontage road between Airport Blvd & US 290/SH 71 |  Nightly from 9 p.m. until 5 a.m. Tuesday, November 14 through Thursday, November 16

Read more on construction phasing and additional project details HERE.


My I35 Traffic Alerts are provided by Central Texas Regional Mobile Authority (CTRMA) & TxDOT.


 