TRAFFIC ALERT: Weekly Traffic, Road Construction Update For IH-35

While construction is tough on everyone, TxDOT is trying to do everything it can to minimize disruptions. TxDOT knows you’ve got to get where you need to go.

I-35 AT FM 3406

The intersection of FM 3406 and the I-35 frontage roads is being improved, and the FM 3406 bridge over I-35 is being reconstructed.

PROJECT ACTIVITY

Closures are weather permitting and updated on Tuesdays and Fridays.

  • Southbound I-35 reduced to one lane under FM 3406 bridge
  • Nightly from 9 p.m. until 5 a.m. Sunday, June 12 until Thursday, June 15
  • FM 3406 right lane closed in each direction between Mays St & Chisholm Trail Rd
  • Westbound closed 9 p.m. until 1 a.m. & eastbound closed 1 a.m. until 5 a.m. Sunday, June 11

FUNDING

  • Construction cost: $12.4 million

SCHEDULE

  • Construction start: March 2017
  • Anticipated construction completion: Spring 2019, weather permitting

CONTRACTOR

  • Flatiron Constructors Inc.

 


 

I-35 FROM US 79 TO SH 45 NORTH

New braided ramps (where one ramp crosses over the other) are being constructed along the northbound I-35 mainlanes between Hester’s Crossing and RM 620 to eliminate merging conflicts. The northbound and southbound intersections of US 79 and the I-35 frontage roads are also being reconstructed to add a third left-turn for westbound US 79.

PROJECT ACTIVITY

Closures are weather permitting and updated on Tuesdays and Fridays.

  • Northbound I-35 reduced to one right lane between Brushy Creek & RM 620
  • 9 p.m. Monday, June 12 to 4 a.m. Tuesday, June 13
  • Various closures northbound I-35 between Hesters Crossing & RM 620 exit ramp. A new temporary entrance ramp will open Wednesday, June 14.
  • 9 p.m. Monday, June 12 to 5 a.m. Tuesday, June 13
  • I-35 exit ramps in both directions on SH 45N will close. Use previous ramps and follow frontage road to reach I-35.
  • Nightly from 9 p.m. until 5 a.m. Monday, June 12 through Tuesday, June 13

CONSTRUCTION PHASING

  • Phase 1: (currently in this phase)

° Improving US 79/I-35 intersection

° Constructing temporary entrance/exit ramps at RM 620 and Hester’s Crossing

° Constructing new braided ramps between SH 45N and RM 620

  • Phase 2:

° Tying new ramps into I-35 mainlanes

  • Phase 3:

° Final paving

FUNDING

  • Construction cost: $28.1 million (State Proposition 1)

SCHEDULE

  • Construction start: July 2016
  • Anticipated construction completion: Spring 2019, weather permitting

CONTRACTOR

  • Capital Excavation Company 

 


I-35 AT OLTORF STREET

Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads, constructing new extended entrance/exit lanes for mainlanes and ramps, and adding U-turns in both directions at Oltorf Street. Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.

PROJECT ACTIVITY

Closures are weather permitting and updated on Tuesday and Fridays.

  • Northbound I-35 reduced to one lane between Woodward St & Woodland Ave. The entrance ramp from Woodward St closed.
  • Nightly from 9 p.m. until 5 a.m. Wednesday, June 14 through Thursday, June 15
  • Southbound I-35 frontage road right lane closed between Algarita Ave & Woodward St exit ramp.
  • 10 p.m. Monday, June 12 to 6 a.m. Tuesday, June 13
  • Northbound I-35 Woodland Ave exit #232B closed
  • Until June 2017
  • Northbound I-35 reduced to one lane between Woodland Ave & Holly St. The Riverside Dr & Holly St exits will close as well as the following entrance ramp will close Tuesday night.
  • Nightly from 9 p.m. until 5 a.m. Monday, June 12 through Tuesday, June 13

CONSTRUCTION PHASING:

  • Phase 1: (currently in this phase)

° Widen northbound and southbound I-35 mainlanes for extended entrance/exit lanes

° Begin northbound frontage road and Oltorf Street entrance ramp improvements

  • Phase 2:

°Reconstruct Oltorf Street bridge and add new U-turns

  • Phase 3:

° Construct southbound entrance and exit ramps south of Oltorf Street

° Southbound frontage road improvements

  • Phase 4:

° Construct southbound entrance ramp north of Oltorf Street

° Complete frontage road construction

° Final paving operations

FUNDING

  • Construction cost: $42.6 million (Congestion Relief Initiative)

SCHEDULE

  • Construction start: February 2017
  • Anticipated construction completion: Winter 2019/2020, weather permitting

CONTRACTOR

  • OHL, USA, Inc.

I-35 FROM STASSNEY LANE TO WILLIAM CANNON DRIVE

The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek. New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 mainlanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging. Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed. Click here to view the I-35 from Stassney Lane to William Cannon Drive Smart Work Zone Traffic Camera.

PROJECT ACTIVITY

  • Closures are weather permitting and updated on Tuesday and Fridays.
  • Southbound I-35 left lane closed in both directions between US 290/SH 71 & Slaughter Ln
  • Nightly from 9 p.m. until 5 a.m. northbound & 10 p.m. until 6 a.m. southbound Monday, June 12 through Thursday, June 15

CONSTRUCTION PHASING

  • Phase 1: (currently in this phase)

° Pave inside median area

° Construct extended entrance/exit lanes

° Widen mainlanes and add shoulders

° Build U-turn bridges at Stassney Lane and William Cannon Drive

  • Phase 2:

° Construct new Stassney Lane bridge

  • Phase 3:

° Construct new William Cannon Drive bridge

° Final paving operations

FUNDING

  • Construction cost: $78.8 million (State Proposition 1)

SCHEDULE

  • Construction start: July 2016
  • Anticipated construction completion: Winter 2019/2020, weather permitting

CONTRACTOR

  • OHL, USA, Inc.

I-35 FRONTAGE ROAD PAVING FROM SH 45 NORTH TO RUNDBERG LANE

Frontage road paving northbound and southbound I-35 from SH 45 North to Rundberg Lane.

PROJECT ACTIVITY

Closures are weather permitting and updated on Tuesday and Fridays.

  • Northbound I-35 frontage road right lane closed at The Lakes Blvd
  • weekdays from 9 a.m. until 3 p.m. through Monday, June 19
  • Southbound I-35 frontage road right lane closed between Braker Ln & Rundberg Ln
  • 9 p.m. Monday, June 12 to 5 a.m. Tuesday, June 13
  • Northbound I-35 frontage road right lane closed between Rundberg Ln & Yager Ln. Various exits will close as needed.
  • 9 p.m. Monday, June 12 to 5 a.m. Tuesday, June 13
  • Northbound I-35 frontage road right lane closed between Rundberg Ln & Wells Branch Pkwy. Exit #241 & #247 will close as needed.
  • Nightly from 9 p.m. until 5 a.m. Tuesday, June 13 through Thursday, June 15

My I35 Traffic Alerts are provided by Central Texas Regional Mobile Authority (CTRMA) & TxDOT.