Weekly Road Construction Projects Affecting San Marcos Traffic

Weekly Road Construction Projects Affecting San Marcos Traffic

January 22 – 28, 2017

 

LOCATION BEGIN DATE EST. END DATE
ROAD CLOSURES    
MLK PARADE: The Martin Luther King Parade will be held on Monday, Jan. 16 from 10 a.m. – 11 a.m. Parade will start on W. San Antonio at Guadalupe then continue on N. LBJ to MLK and finish at Dunbar Park. Dunbar Heritage Association, 512.694.5292 Jan. 16 @ 10 a.m. Jan. 16 @ 11 a.m.
DUTTON DRIVE: Both sides of the street, approx. 150’ north of intersection at Wonder World Drive will be closed intermittently for utility construction on Jan. 10 – 24 from 7 a.m. – 5:30 p.m. LJ Cross Plumbing, 512.263.4222 Jan. 10 @ 7 a.m. Jan. 24 @ 5:30 p.m.
417 COMANCHE: All lanes in both directions at the 400 blk of Comanche between Lindsey and Pat Garrison will be closed on January 16 – 20 from 7 a.m. – 4 p.m. for construction maintenance. Be aware of flaggers. Skyline builders/Matthew Ostrowski, 512.699.6465 Jan. 17 @ 7 a.m  Jan. 20 @ 4 p.m.
E. HUTCHISON/EDWARD GARY: E. Hutchison St. will be closed on the east side of Edward Gary for a water/wastewater tie in on December 19 through January 13, 2017 from 7 a.m. – 9 p.m. EMJ Construction, 423.855.1550 Dec. 19 @ 7 a.m. Jan. 13 @ 9 p.m.
SESSOM DR: There will be single lane closures from N. LBJ to Aquarena Springs on January 15 through March 31, weather permitting, from 8 a.m. to 5 p.m. daily for overhead utility work. CenturyLink, 903.675.0406 Jan. 15 @ 8 a.m. March 31 @ 5 p.m.
400 BLK SARA ST: The 400 block of Sara St. will be closed to traffic on Monday, Jan. 16 from 2 p.m. – 11 p.m. for a MLK Charity event. Michael Howard, 214.529.5263 Jan. 16 @ 2 p.m. Jan. 16 @ 11 p.m.
N LBJ:  From Holland St. to Camaro Way will be closed to through traffic until the Spring of 2017. Road closure will occur during daytime construction hours. City contractor will be replacing utility lines in the area. Through traffic including Emergency Vehicles, will be routed around the project limits; please follow the detours. Engineering/Capital Improvements, 512.393.8130 Present Spring 2017
WOODS ST: A segment of Woods St between Comanche and North Street will be closed during construction of the new Texas State University Engineering & Science Building beginning Monday, August 15 until August 2018. Project Manager Scott Rouse, 512.245.2202 Aug 15, 2016 August 2018
EAST SAN ANTONIO STREET: Half a block closed from the alley to N. LBJ every Saturday from 8 a.m. – 3 p.m. for the Farmers Market on the Square. Main Street Program, 512.393.8430. Year Round

Year Round

Related Articles