What To Expect On San Marcos Roads During Week Of Sunday, Oct. 8 – Saturday, Oct. 14

San Marcos’ Weekly Road Construction & Traffic Report

Short & Long Term Road Construction Projects Affecting San Marcos Traffic Sunday, October 1  – Saturday, October 7, 2017

Can’t see the whole table? Touch it and scroll right.

WEEKLY ROAD CONSTRUCTION SCHEDULE 

zzz

LOCATION BEGIN DATE EST. END DATE
HOFHEINZE STREET: Please watch for heavy equipment and construction workers on the street. Please park vehicles off the street or it may be towed at your own expense. Please drive slowly, use caution in the work zone and obey traffic control flagmen. City of San Marcos Street Dept., 512.393.8025    Oct. 17      8 a.m.     Nov. 17      6 a.m. 
LP 82/AQUARENA SPRINGS: LP 82/Aquarena Springs between Charles Austin Dr. to Post Road will have single lane closure. TxDOT 512. 832.7027.    Oct. 9     9 a.m.  Oct. 10 3:30 p.m. 
BISHOP ST: 200 Block of N Bishop will have west side lane closure with flagger control for utility work on west side lane. One lane will be shut down with flagger. Centurylink 512.754.5223       Oct. 2       4 p.m.     Oct. 28     8 a.m.
OAK HEIGHTS NEIGHBORHOOD SLURRY SEAL STREET RESURFACING PROJECT: Please watch for heavy equipment and construction workers on the street. Be aware of temporary street closures and detours. Door hangers will be distributed 24 hours prior to the resurfacing of your street. Please park vehicles off the street or it may be towed at your own expense. Please drive slowly, use caution in the work zone and obey traffic control flagmen. City of San Marcos Street Dept., 512.393.8025. Sept. 29   Oct. 6   
SOUTHWEST HILLS NEIGHBORHOOD SLURRY SEAL STREET RESURFACING PROJECT: Please watch for heavy equipment and construction workers on the street. Be aware of temporary street closures and detours. Door hangers will be distributed 24 hours prior to the resurfacing of your street. Please park vehicles off the street or it may be towed at your own expense. Please drive slowly, use caution in the work zone and obey traffic control flagmen. City of San Marcos Street Dept., 512.393.8025.    Sept. 29    5 a.m.    Oct. 6     2 p.m.
HOLLAND HILLS NEIGHBORHOOD SLURRY SEAL STREET RESURFACING PROJECT: Please watch for heavy equipment and construction workers on the street. Be aware of temporary street closures and detours. Door hangers will be distributed 24 hours prior to the resurfacing of your street. Please park vehicles off the street or it may be towed at your own expense. Please drive slowly, use caution in the work zone and obey traffic control flagmen. City of San Marcos Street Dept., 512.393.8025. Sept. 29    Oct. 6 
BROADWAY STREET/SUNSET ACRES NEIGHBORHOOD SLURRY SEAL STREET RESURFACING PROJECT: Please watch for heavy equipment and construction workers on the street. Be aware of temporary street closures and detours. Door hangers will be distributed 24 hours prior to the resurfacing of your street. Please park vehicles off the street or it may be towed at your own expense. Please drive slowly, use caution in the work zone and obey traffic control flagmen. City of San Marcos Street Dept., 512.393.8025.  Sept. 29   8 a.m.  Oct. 6  
BISHOP ST: Bishop St. from Belvin St. to Prospect St. will be closed for electricity utility work. Traffic will be detoured to Clara St. SMEU, 512-393-8300.    Oct. 3     7 a.m.   Oct. 13   4 p.m.
BROADWAY ST: Broadway St. will be closed from Staple Rd. to SH 123 for Utility installation. Rockin Q Construction 512.738.6666 Sept. 18 Sept. 29
POST ROAD: The Blanco River Bridge was closed on July 24 for new bridge construction. Traffic needs to detour to alternative routes. Hays County. July 24 NOT LISTED
LONG TERM CLOSURE – MCKIE ST: Mckie St. will be closed from IH35 frontage Rd. to apartment entrance for utility installation. Rockin Q Construction 512.738.6666    July 24     7 a.m.     Dec. 1      5 p.m.
LONG TERM CLOSURE – VISTA ST: All lanes in both directions will be closed from 310 – 312 Vista Street for utility construction Texas State University, 512.245.2202. Present    July 31    2018
LONG TERM CLOSURE – SESSOM DR: Various lane closures from N. LBJ to Aquarena Springs Dr. for road construction. City of San Marcos Engineering/CIP Dept., 512.393.8130. Present  Jan.   2018
LONG TERM CLOSURE – N LBJ:  From Holland St. to Camaro Way, this road closure will occur during daytime construction hours. City contractor will be replacing utility lines in the area. Through traffic including Emergency Vehicles, will be routed around the project limits; please follow the detours. Engineering/Capital Improvements, 512.393.8130. Present Summer 2017
LONG TERM CLOSURE – WOODS ST: A segment of Woods St between Comanche and North Street will be closed during construction of the new Texas State University Engineering & Science Building. Project Manager Scott Rouse, 512.245.2202. August 2015 August 2018
LP 82/AQUARENA SPRINGS: TxDOT introduced a new traffic signal at the intersection of Post/Bobcat traffic will be detoured to the new signal. TxDOT, 512.393.8130.     Feb.     2017 Spring 2018
LONG TERM CLOSURE – EAST SAN ANTONIO STREET – EVERY SATURDAY: Half a block closed from the alley to N. LBJ every Saturday from 8 a.m. – 3 p.m. for the Farmers Market on the Square. Main Street Program, 512.393.8430. Year  Round Year Round

 