Essential Road Construction, Traffic Alerts For Your I-35 Corridor

TxDOT, My I35 Weekly Corridor Traffic and Road Construction Weekly Update —Including Northbound maintenance on Yarrington Road and RM 150…


TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.

I-35 CORRIDOR ROAD CONSTRUCTION UPDATE

SUNDAY 7/29 – SATURDAY 8/4



I-35 FROM STASSNEY LANE TO WILLIAM CANNON DRIVE

PROJECT OVERVIEW | The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 mainlanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.

Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting

  • Northbound I-35 frontage road right lane closed between William Cannon Dr. and Nelms Dr. | Through August 2018, weather permitting

 

  • Various southbound I-35 frontage road closures at Stassney Ln. | 8 PM until 6 AM Thursday, July 26 through Friday, July 27

 

  • Alternating I-35 frontage road closures in both directions across Stassney Ln. | 8 PM until 6 AM Thursday, July 26 through Friday, July 27

 

  • I-35 closed in both directions at William Cannon Dr. Use alternate route. | 10 PM until 9 AM Friday, July 27th and 11 p.m. until 10 a.m. Saturday, July 28th

 

  • Northbound I-35 frontage road left lane closed approaching William Cannon Dr. | 9 PM until 5 AM Sunday, July 29 through Monday, July 30

 

  • Southbound I-35 frontage road left lane closed at William Cannon Dr. | 9 PM until 5 AM Sunday, July 29 through Tuesday, July 31

 

  • Northbound I-35 right lane closed at Slaughter Ln. entrance ramp. Use alternate exit. | 9 PM until 5 AM Sunday, July 29 through Tuesday, July 31

 

  • I-35 reduced to one lane in both directions under William Cannon Dr. | 10 PM until 6 AM Sunday, July 29 through Monday, July 30

 

  • Northbound I-35 frontage road left lane closed at the William Cannon Dr. exit (228). Use alternate exit. | 8 PM until 5 AM Wednesday, August 1 through Thursday, August 2

 

  • Northbound I-35 frontage road left lane closed between Stassney Ln. and Teri Rd. | 9 PM until 5 AM Wednesday, August 1 through Thursday, August 2

 

  • Northbound I-35 right should closed between William Cannon Dr. exit and the following entrance ramp. | 9 AM until 3 PM through Thursday, August 2

 

  • Northbound I-35 left lane closed at the Slaughter Ln. entrance ramp. | 9 AM until 3 PM Thursday, August 2 through Friday, August 3

 

  • William Cannon Dr. closed across I-35. | 8 PM until 10 AM Friday, July 27 through Sunday, July 29

Read more on construction phasing and additional project details HERE.



I-35 AT OLTORF ST.

PROJECT OVERVIEW | Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads, constructing new extended entrance/exit lanes for mainlanes and ramps, and adding U-turns in both directions at Oltorf Street.

Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 right lane closed between Woodland Ave. exit and Mariposa St. | 9 PM until 5 AM Thursday, July 26 through Friday, July 27

 

  • Northbound I-35 frontage road right lane closed between Oltorf St. and the Woodland Ave exit. | 8 PM until 5 AM Sunday, July 29 through Thursday, August 2

 

  • Southbound I-35 frontage road closed between Oltorf St. and Woodward St. Watch for flaggers. | 8 AM until 5 PM Monday, July 30 through Friday, August 3

 

  • Northbound I-35 frontage road closed between SH 71 and Woodward St. | 9 AM until 3 PM Monday, July 30 through Friday, August 3

 

  • Northbound I-35 right shoulder closed between Woodland Ave. exit and Mariposa St. | 9 PM until 5 AM Tuesday, July 31 through Wednesday, August 1

 

  • Southbound I-35 frontage road reduced to one lane at St. Edwards Dr. Watch for flaggers. | 8 PM until 5 AM Tuesday, July 31 through Wednesday, August 1

Read more on construction phasing and additional project details HERE.



I-35 FROM RUNDBERG LN. TO US 290 EAST

PROJECT OVERVIEW | This project includes main-lanes and frontage road reconstruction and the addition of three new flyovers at US 183.

The project also includes reconstruction of the St. Johns Avenue Bridge, the addition of frontage road U-turns on both sides, intersection bypass lanes under St. Johns Avenue in both directions, extended entrance/exit lanes, and ramp and shoulder improvements.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Powell Ln closed at I-35. Detour via Wonsley Dr. | 9 PM until 5:30 AM through August 30

 

  • Northbound I-35 frontage road right lane closed between St. Johns Ave. and US 183. | 9 AM until 3 PM weekdays through August 3

 

  • I-35 frontage road closed in both directions between St. Johns Ave. and Delmar Ave. Blackson Ave. will also be closed. | Intermittently from 6 AM until 10 AM Sunday, July 29

 

  • I-35 frontage road closed in both directions near Blackson Ave. | Intermittently from 6:30 AM until 9 AM Sunday, July 29

 

  • Various northbound I-35 frontage road closures between US 183 and Rundberg Ln. The Rundberg Ln. exit will also be closed. | 9 PM until 5 AM Sunday, July 29 through Thursday, August 2

 

  • Southbound I-35 frontage road right lane closed between Huntland Dr. and US 290 E. | 9 AM until 3 PM Monday, July 30 through Friday, August 3

Read more on construction phasing and additional project details HERE.



I-35 AT FM 3406

PROJECT OVERVIEW | The intersection of FM 3406 and the I-35 frontage roads are being improved, and the FM 3406 bridge over I-35 is being reconstructed.

The FM 3406 (Old Settlers Blvd) bridge will close to eastbound traffic. Westbound traffic will detour to the newly constructed U-turn Bridge. | Until summer 2018, weather permitting.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting

  • I-35 reduced to one lane in both directions under FM 3406/Old Settlers Blvd. | 9 p.m. until 5 a.m. Sunday, July 29 through Thursday, August 2

Read more on construction phasing and additional project details HERE



I-35 MAINTENANCE PROJECTS

PROJECT ACTIVITY | These lane closures are associated with on going maintenance activities throughout the corridor.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting

  • Northbound I-35 reduced to one lane between Yarrington Rd. & RM 150. | 9 p.m. until 5 a.m. Sunday, July 29 through Thursday, August 2

Read more on construction phasing and additional project details HERE.


My I35 Traffic Alerts are provided by Central Texas Regional Mobile Authority (CTRMA) & TxDOT.


Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button