San Marcos road construction, detours, closures for week of May 24

Staff

The short & long term road construction projects that could affect your drive… Please use caution, drive slowly, and watch for heavy equipment, construction workers, and traffic control flaggers.

  • All traffic projects may be subject to delays or extensions due to weather and/or the current Public Health situation.

.

RECURRING WEEKLY CLOSURES

EAST SAN ANTONIO STREET — FARMERS MARKET
EVERY SATURDAY | 7:30 AM – 3 PM
Half a block of the street closed from the Alley to N. LBJ for the Farmers Market on the Square. Main Street Program 512.393.8430.

 

SHORT TERM ROAD PROJECTS
.

CLOVIS BARKER ROAD | JUNE 1 – JUNE 2 | 7 AM – 7 PM
Clovis Barker Road from Hwy 123 to IH 35 will have a single lane closure for roadway resurfacing. For more information contact, Public Services and Transportation at 512.393.8036.

OLD RANCH ROAD 12 | JUNE 2 – 4 | 7 AM – 7 PM
Old Ranch Road 12 from Craddock Avenue to Ranch Road 12 will have a single lane closure for roadway resurfacing. For more information contact, Public Services and Transportation at 512.393.8036.

BURLESON STREET | MAY 25 – 26 | 8 AM – 5 PM
 Burleson Street at Prospect Street will be closed for utility work. For information about this closure, contact the City of San Marcos Water/Wastewater Department at 512.393.8010.

 

LONG TERM ROAD PROJECTS

 

VICTORY GARDENS UTILITY PROJECT | MAY 2021 | 7 AM – 5 PM
Victory Gardens Neighborhood will undergo a new underground utility installation. The street and sidewalk closure will affect Patton Street, Knox Street, and Invasion Street. For more information call Darren with Cox Commercial Construction at 956.601.1645.
.

HOPKINS STREET | MAY 2020 — SPRING OF 2022
Hopkins Street between Bishop Street and Moore Street will be closed to vehicle and pedestrian traffic for a Street Reconstruction Project. Traffic will be detoured to Craddock at both ends of the project, with only local traffic allowed. Phase 2 is starting and is extending the closure for local traffic from Bishop to Johnson Street. The overall completion of the project is anticipated by Spring 2022. For more information call Richard Reynosa with the City of San Marcos Engineering Department at 512.393.8235.
.

HOPKINS STREET | CURRENT — AUGUST 2021 | 9 AM – 3 PM
CM Allen to Thorpe will have intermittent single lane and sidewalk closures for sidewalks and driveway installation. For more information call Brad Bechtol with Mac Inc at 512.350.3767.
.

UHLAND ROAD | MARCH 2021 — JULY 2021
1396 Uhland Road to Aquarena Springs Road will be closed to vehicle and pedestrian traffic for a Road Reconstruction Project. For more information call Todd Keltgen at 512.212.7990.
.

UHLAND ROAD | MARCH 2021 — JUNE 2021 | 8 AM – 5 PM
The Eastbound lane of the 1000 block of Uhland Road will be closed to vehicle and pedestrian traffic for a Utility Line Relocation. For more information call HMI Utilities at 940.255.7705.
..

GUADALUPE STREET IMPROVEMENTS | CURRENT
Sidewalk closed from Guadalupe Street at Martin Luther King Drive to the railroad crossing for reconstruction. Completion is expected by end of summer. Chris Gonzalez – New Age General Contractors, Inc. at 830-560-9077.

 