The Top 13 Streets To Avoid In San Marcos This Week

Top 12 Streets To Avoid This Week In San Marcos — The Long & Short Term Road Construction Projects That Could Affect You Drive…

Please use caution, drive slowly and watch for heavy
equipment, construction workers, and traffic control flaggers.

Source: City of San Marcos

Can’t see the whole table? Touch it and scroll right.
z

WEEKLY ROAD CONSTRUCTION SCHEDULE

LOCATION BEGIN DATE EST. END DATE
HOPKINS ST.:Hopkins Street will have road closure for utility pole installation. San Marcos Electricity, 512.393.8383 Sept 4
9 AM
Sept. 30
4 PM
HOPKINS ST.: Hopkins Street from Cheatham Street to Charles Austin Drive will be reduced to one lane in both directions for repaving. Austin Materials, Shane Ramey, 512.621.5259 Sept. 12
8 PM
Sept. 14
5 AM
VISTA STREET: Vista street will have all lanes in both directions will be closed from 310 – 312 for utility construction. Texas State University, 512.245.2202 Present
8 AM
Completion Date
TBD
MCKIE STREET: 600 McKie St. from Mariposa to IH-35 Frontage Road will have a lane closure for Utility installation. Rockin Q Construction, 512.738.6666
Sept. 4
7 AM
Sept. 14
6 PM
LONG TERM CLOSURE – CHEATHAM STREET: 500 Cheatham Street from Riverside to CM Allen will have a westbound lane closure for Waterline installation. Santa Clara Construction, Jacob Snyder, 214.298.4578 Sept. 4
7 AM
Nov. 1
5 PM
LONG TERM CLOSURE – STUDENT CENTER DRIVE: Student Center Drive from Matthews to the North Loading Dock of the Alkek Library will be closed for the expansion of the LBJ Student Center. Service and delivery access to Alkek Library and Derrick Hall loading docks will be available, via Russell and Pickard Streets. Texas State University, 512.245.2202
Current Jan. 21
2020
LONG TERM CLOSURECAMACHO STREET: The 200 and 300 Blocks of Camacho Street will be closed for Utility Installation. Cox Commercial Construction, 956-601-1645 Sept. 10
7 AM
Oct. 5
5 PM
LONG TERM CLOSURE – CHEATHAM STREET & GUADALUPE: The 100 Block of Eastbound Cheatham Street will be closed, and the 400-500 Blocks of Guadalupe will have partial lane closures for new construction. Cheatham Street L.P., Gary Bellomy, 512.694.8839 Present
Dec. 31
2018


LONG TERM CLOSURE – OAK RIDGE DRIVE: Oak Ridge Dr. will have single lane closures daily for utility installation. COSM Engineering/CIP Dept., 512.393.8130 Present Sept.
3:30 PM
LONG TERM CLOSURE MCKIE STREET: McKie St. will be closed from IH-35 Frontage Rd. to apartment entrance for utility installation. Rockin Q Construction, 512.738.6666 Current
8 AM
Dec. 7
5 PM
LONG TERM CLOSURE – CONCHO STREET: Eastbound Concho Street between LBJ and Guadalupe will be closed, LBJ and Guadalupe will also have narrow lanes between University Drive and Concho Street, through the summer of 2020 for Construction. 3411 Builders, Inc., Richard Bagby, 832.449.0328
Aug. 6
2018


July
2020
LONG TERM CLOSURE – CM ALLEN: CM Allen between University Drive and Hopkins Street will be closed for the Reconstruction of the Roadway. COSM Engineering/CIP Dept., 512.393.8130 July 25
9 AM
Apr. 2019
5 PM
**CLOSURE EVERY SATURDAY – EAST SAN ANTONIO STREET: Half a block closed from the alley to N. LBJ every Saturday from for the Farmers Market on the Square. Main Street Program, 512.393.8430 Every
Saturday
8 AM
Every
Saturday
3 PM


 

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button