I35 Corridor Weekly Road Construction Alerts For Saturday, July 29 – Friday, Aug. 4

TxDOT, My I35 and Central Texas Regional Mobility Authority’s Weekly Corridor Traffic and Road Construction Update for the IH-35 Corridor

TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do everything they can to minimize disruptions. TxDOT knows you’ve got to get where you need to go.

 



I – 3 5   F R O M   U S   7 9   T O   S H   4 5  N O R T H

New braided ramps (where one ramp crosses over the other) are being constructed along the northbound I-35 mainlanes between Hester’s Crossing and RM 620 to eliminate merging conflicts.

The northbound and southbound intersections of US 79 and the I-35 frontage roads are also being reconstructed to add a third left-turn for westbound US 79.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting and updated on Fridays.

  • Northbound I-35 reduced to one lane between RM 620 & Westinghouse Rd — Nightly from 9 p.m. until 5 a.m. Sunday, July 30 through Friday, August 4

 

Read more on construction phasing and additional project details HERE.



I – 3 5   A T   5 1  S T   S T R E E T

Work includes adding a southbound intersection bypass lane to allow through-traffic to bypass the traffic signal, re-configuring the entrance/exit ramps, and realigning the southbound frontage road to add a new roundabout that improves traffic flow and safety.

Bicycle and pedestrian enhancements will also be made within the project limits.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting and updated on Fridays.

  • Southbound I-35 reduced to one lane between US 290 and Airport Blvd. Ramps near 51st St & Airport Blvd will also close — 9 p.m. Monday, July 24 to 5 a.m. Tuesday, July 25

 

  • Northbound I-35 ramps between Barbara Jordan Dr & E 52nd St closed — 10 p.m. Monday, July 31 to 4 a.m. Tuesday, August 1

Read more on construction phasing and additional project details HERE.



I – 3 5   A T   O L T O R F   S T R E E T

Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads, constructing new extended entrance/exit lanes for mainlanes and ramps, and adding U-turns in both directions at Oltorf Street.

Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting and updated on Fridays.

 

    • Southbound I-35 frontage road right lane closed between Woodland Ave and Mariposa — Daily from 9 a.m. until 3 p.m. Monday, July 31 through Friday, August 4
  •  
    • Southbound I-35 reduced to one lane between Algarita Ave & entrance ramp south of Oltorf — Nightly from 10 p.m. until 6 a.m. Sunday, July 30 through Friday, August 4
  •  
    • Northbound I-35 right lane closed between Oltorf St exit and entrance ramp — Nightly from 9 p.m. until 5 a.m. Sunday, July 30 through Thursday, August 3
  •  
    • Northbound I-35 frontage road left lane closed between Woodward St & the next entrance ramp — Daily from 9 a.m. until 3 p.m. Monday, July 31 through Friday, August 4

Read more on construction phasing and additional project details HERE.



I – 3 5   F R O M   S T A S S N E Y   L A N E   T O   W I L L I A M   C A N N O N   D R I V E

The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 mainlanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.

Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed. 

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting and updated on Fridays.

  • Southbound I-35 left lane closed between Shelby Ln & Stassney Ln. The entrance ramp before Stassney Ln will also close. — 9 a.m. to 3 p.m. Wednesday, August 2 

 

  • Southbound I-35 frontage road right turn lane closed between Williamson Creek to Stassney Ln — Daily from 9 a.m. until 3 p.m. Wednesday, August 2 through Friday, August 4

 

  • Eastbound William Cannon right lane & right turn lane to southbound I-35 frontage road closed — 9 a.m. to 3 p.m. Monday, July 31

 

  • Northbound I-35 frontage road left lane closed between Stassney Ln & William Cannon — Daily from 9 a.m. until 3 p.m. Monday, July 31 & Tuesday, August 1

 

  • Alternating lane closures on Chapparal Rd at I-35 southbound frontage road — 9 a.m. to 3 p.m. Monday, July 31

 

  • I-35 ramps in both directions to eastbound US 290 closed. Detour to frontage road to reach US 290. — Nightly from 8 p.m. until 5 a.m. Sunday, July 30 & Tuesday, August 1

 

  • Northbound I-35 right lane closed at Stassney Ln. The exit ramp north of Stassney Ln will also close. — Daily from 9 a.m. until 3 p.m. Monday, July 31 & Tuesday, August 1

 

Read more on construction phasing and additional project details HERE.



                                       M A I N T E N A N C E :   I – 3 5   F R O N T A G E   R O A D   P A V I N G                                                                                                       F R O M   S H  45  N O R T H   T O   R U N D B E R G   L A N E

 

Frontage road paving northbound and southbound I-35 from SH 45 North to Rundberg Lane.

• THIS WEEK’S PROJECT TRAFFIC ADVISORY • 

 

Closures are weather permitting and updated on Fridays.

  • Northbound I-35 frontage road right lane closed between Braker Ln & SH 45N/Louis Henna Blvd — 9 p.m. Sunday, July 30 to 5 a.m. Monday, July 31

 

  • Southbound I-35 frontage road right lane closed between SH 45N/Louis Henna Blvd & Rundberg Ln — Nightly from 9 p.m. to 5 a.m. Monday, July 31 through Wednesday, August 2

 

Read more on construction phasing and additional project details HERE.



I – 3 5   A T   F M   3 4 0 6

The intersection of FM 3406 and the I-35 frontage roads are being improved, and the FM 3406 bridge over I-35 is being reconstructed. 

• THIS WEEK’S PROJECT TRAFFIC ADVISORY •

Closures are weather permitting and updated on Fridays.

  • Southbound I-35 reduced to one lane under FM 3406 bridge —Nightly from 9 p.m. until 5 a.m. Sunday, July 30 through Thursday, August 3

Read more on construction phasing and additional project details HERE.

 



My I35 Traffic Alerts are provided by Central Texas Regional Mobile Authority (CTRMA) & TxDOT.

 