Top I-35 Construction Detours & Closures For Your Weekly Commute

.
TxDOT knows you’ve got to get where you need to go.

While construction is tough on everyone, TxDOT is trying to do
everything they can to minimize disruptions.

Remember to support your local businesses as they are still open during construction…

I-35 CAPITAL AREA CORRIDOR MOBILITY
…..Closures, Detours, Traffic Alerts for July 18 – July 24

.
I-35 AT POSEY ROAD

PROJECT OVERVIEW | This project will construct a new overpass on I-35 over Posey Road, add two new U-turns in each direction at Posey Road, perform ramp reversals and convert two-way frontage roads to one-way.

Currently, the I-35 main lanes go under Posey Road. The new configuration will have the I-35 main lanes going over Posey Road.

  THIS WEEK’S PROJECT TRAFFIC ADVISORY 

Closures are weather permitting

  • Posey Road bridge closed at I-35.
    ° Until further notice
  • Northbound I-35 Posey Road exit (#199) and Centerpoint Road exit (#200) are closed.
    ° Until further notice
  • Southbound I-35 entrance ramp closed permanently at Centerpoint Road.
    ° Until further notice
  • Northbound and southbound I-35 left lane closed nightly from Centerpoint Road to York Creek Road.
    ° Through Thursday, July 25

Read more on construction phasing and additional project details HERE.

I-35 FROM STASSNEY LANE TO WILLIAM CANNON DRIVE

PROJECT OVERVIEW | The project will reconstruct the bridge structures at Stassney Lane and William Cannon Drive, as well as the frontage road bridge over Williamson Creek.

New U-turn bridges will be added in both directions at Stassney Lane and William Cannon Drive, and the I-35 main lanes will be widened to incorporate shoulders and extended entrance/exit lanes to allow for better merging.

Bicycle and pedestrian enhancements are also being made, and new safety lighting is being installed.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 frontage road right lane closed from the Slaughter Lane entrance ramp to Stassney Lane.
    ° Monday, July 20 through Saturday, July 25 from 9 AM until 3 PM
  • Southbound I-35 frontage road right lane closed from Stassney Lane to William Cannon Drive.
    ° Monday, July 20 through Saturday, July 25 from 9 AM until 3 PM
  • Southbound I-35 frontage road right lane closed from William Cannon Drive to Chaparral Road.
    ° Monday, July 20 through Saturday, July 25 from 9 AM until 3 PM
  • Northbound I-35 reduced to one lane from the Slaughter Lane entrance ramp to the William Cannon Drive exit (#228).
    ° Wednesday, July 22 through Thursday, July 23 from 11 PM until 5 AM

Read more on construction phasing and additional project details HERE.

I-35 AT OLTORF ST.

PROJECT OVERVIEW | Improvements include the reconstruction of the Oltorf Street bridge, improving entrance/exit ramps and frontage roads.

Additionally, construction of new extended entrance/exit lanes for main lanes and ramps, and adding U-turns in both directions at Oltorf Street.

Bicycle and pedestrian enhancements will also be made along the I-35 frontage roads in each direction within the project limits.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

…………Closures are weather permitting

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 FROM RUNDBERG LN. TO US 290 EAST

PROJECT OVERVIEW | This project includes main lanes and frontage road reconstruction and the addition of three new flyovers at US 183.

The project also includes reconstruction of the St. Johns Avenue Bridge, the addition of frontage road U-turns on both sides, intersection bypass lanes under St. Johns Avenue in both directions, extended entrance/exit lanes, and ramp and shoulder improvements.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Southbound US 183 Cameron Road exit closed.
    ° Through September
  • Northbound and southbound I-35 reduced to one lane nightly from Rundberg Lane to US 290 East. Multiple entrances and exit ramps will be closed.
    ° Sunday, July 19 through Thursday, July 23 from 8 PM until 5 AM
  • Northbound and southbound I-35 frontage road left lane closed nightly from Rundberg Lane to US 290 East.
    ° Sunday, July 19 through Thursday, July 23 from 8 PM until 5 AM
  • Southbound US 183 frontage road closed nightly from I-35 to Carver Avenue.
    ° Sunday, July 19 through Thursday, July 23 from 9 PM until 5 AM
  • South to north I-35 U-turn closed daily at US 183.
    ° Monday, July 20 through Friday, July 24 from 9 AM until 3 PM
  • Southbound I-35 frontage road right lane closed daily from Blackson Avenue to Huntland Drive.
    ° Monday, July 20 through Friday, July 24 from 9 AM until 3 PM

Read more on construction phasing and additional project details HERE.

I-35 FROM 1431 TO FM 3406 (NORTHBOUND)

PROJECT OVERVIEW | The intersection of FM 3406 and the I-35 frontage roads are being improved, and the FM 3406 bridge over I-35 is being reconstructed.

The FM 3406 (Old Settlers Blvd) bridge will close to eastbound traffic. Westbound traffic will detour to the newly constructed U-turn Bridge.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Northbound I-35 frontage road reduced to one lane from Jeffrey Way to the RM 1431 exit.
    ° Through early 2021

Read more on construction phasing and additional project details HERE.

I-35 FROM US-79 TO SH-45 NORTH

PROJECT ACTIVITY | New braided ramps (where one ramp crosses over the other) are being constructed along the northbound I-35 main lanes between Hesters Crossing and RM 620 to eliminate merging conflicts.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 AT PARMER LANE

PROJECT OVERVIEW | Reduced congestion, improved mobility at Parmer Lane and Lamar Boulevard, operational efficiency, more reliable travel times, lower fuel consumption.

The start date is summer 2019 and is scheduled to be completed summer of 2021. The construction costs are estimated to be $24.6 million.


THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

• NONE AT THIS TIME •

Read more on construction phasing and additional project details HERE.

I-35 CORRIDOR ROAD & HIGHWAY MAINTENANCE

PROJECT OVERVIEW | These lane closures are associated with ongoing maintenance activities throughout the corridor.
.

THIS WEEK’S PROJECT TRAFFIC ADVISORY

Closures are weather permitting

  • Southbound I-35 frontage road right lane closed daily from Luther Lane to 32nd Street.
    ° Saturday, July 18 from 9 a.m. until 3 PM
    ° Monday, July 20 through Tuesday, July 21 from 9 a.m. until 3 PM.
  • Northbound I-35 frontage road right lane closed daily from Old San Antonio Road to Oak Hill Lane.
    ° Friday, July 17 through Thursday, July 23 from 8 AM until 4 PM
  • Northbound I-35 reduced to one lane from Lakeway Drive to FM 972. Multiple exits will be also closed.
    ° Monday, July 20 through Tuesday, July 21 from 8 PM until 6 AM
  • Northbound I-35 reduced to one lane from SH 195 to Ronald Reagan Boulevard.
    ° Wednesday, July 22 through Thursday, July 23 from 8 PM until 6 AM

Read more on construction phasing and additional project details HERE.


Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button